Ryhall 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Essendine | MALLARD PASS SOLAR FARM LIMITED | Solar | 240 | 1 Jan 2028 | Not stated | Consents Approved |
| Graeme Road Solar & BESS | GREENTECH PROJECTS HOLDING UK LIMITED | Storage with solar or wind | 550 | 30 Oct 2038 | Not stated | Scoping |
Recent changes
- Graeme Road Solar & BESSEngland and Wales, Storage with solar or windCustomer changed from Greentech Services Limited to GREENTECH PROJECTS HOLDING UK LIMITED
- Graeme Road Solar & BESSEngland and Wales, Storage with solar or windCustomer changed from GREENTECH PROJECTS HOLDING UK LIMITED to Greentech Services Limited
- Graeme Road Solar & BESSEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2038 to 30 Oct 2038 (1 day earlier)
- EssendineEngland and Wales, SolarConnection point changed from Ryhall (Network Rail) GSP to Ryhall 400kV Substation
- EssendineEngland and Wales, SolarStatus changed from Scoping to Consents Approved
- Graeme Road Solar & BESSEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2034 to 31 Oct 2038 (+48 months)+48 mo
- Graeme Road Solar & BESSEngland and Wales, Storage with solar or windAdded to the registerNew
- EssendineEngland and Wales, SolarConnection point changed from Ryhall to Ryhall (Network Rail) GSP
- EssendineEngland and Wales, SolarCustomer changed from WINDEL SOLAR 3 LTD to MALLARD PASS SOLAR FARM LIMITED
- EssendineEngland and Wales, SolarAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?