Graeme Road Solar & BESS
GREENTECH PROJECTS HOLDING UK LIMITED at Ryhall 400kV Substation
- Connection date
- 30 Oct 2038
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 550 MW
- Connected now
- 0 MW
- Still to connect
- 550 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-004375
- In the register since
- January 2024
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 23 Jan 2026 registerCustomer changed from Greentech Services Limited to GREENTECH PROJECTS HOLDING UK LIMITED
- 19 Dec 2025 registerCustomer changed from GREENTECH PROJECTS HOLDING UK LIMITED to Greentech Services Limited
- 24 Dec 2024 registerConnection date moved from 31 Oct 2038 to 30 Oct 2038 (1 day earlier)
- 29 Oct 2024 registerConnection date moved from 31 Oct 2034 to 31 Oct 2038 (+48 months)
- 30 Jan 2024 registerAdded to the register
Also at Ryhall 400kV Substation
Substation view1 other project, 790 MW still to connect at this substation in total. 240 MW is due to connect here before this project’s connection date of 30 Oct 2038.