Rothienorman 400kV Substation
North Scotland, SSEN Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Rothienorman Battery | BLACKFORD RENEWABLES LTD | Storage | 500 | 30 Jul 2029 −51 mo | Gate 1 | Scoping |
| Rothienorman Sync Comp | ROTHIENORMAN GRID SERVICES LIMITED | Other | 0 | Connected | Not stated | Built |
Left the register since January 2021: Rothienorman Flexpower Synchronous Compensation (0 MW).
Recent changes
- Rothienorman BatteryNorth Scotland, StorageConnection date moved from 31 Oct 2033 to 30 Jul 2029 (−51 months)−51 mo
- Rothienorman BatteryNorth Scotland, StorageMarked as Gate 1
- Rothienorman BatteryNorth Scotland, StorageCustomer changed from Rothienorman Flexpower A Ltd to BLACKFORD RENEWABLES LTD
- Rothienorman Sync CompNorth Scotland, OtherConnection date removed (was 31 Oct 2024)
- Rothienorman Sync CompNorth Scotland, OtherStatus changed from Consents Approved to Built
- Rothienorman Sync CompNorth Scotland, OtherConnection date moved from 31 Mar 2024 to 31 Oct 2024 (+7 months)+7 mo
- Rothienorman BatteryNorth Scotland, StorageCustomer changed from ROTHIENORMAN FLEXPOWER LTD to Rothienorman Flexpower A Ltd
- Rothienorman Flexpower Synchronous CompensationNorth Scotland, OtherLeft the register (0 MW from 15 Jul 2024)0 MW
- Rothienorman BatteryNorth Scotland, StorageSubstation name updated in the register (from Rothienorman 400kV to Rothienorman 400kV Substation)
- Rothienorman Sync CompNorth Scotland, OtherSubstation name updated in the register (from Rothienorman 400kV to Rothienorman 400kV Substation)
- Rothienorman Flexpower Synchronous CompensationNorth Scotland, OtherSubstation name updated in the register (from Rothienorman 400kV to Rothienorman 400kV Substation)
- Rothienorman BatteryNorth Scotland, StorageStage removed (50 MW from 31 Oct 2024)
- Rothienorman BatteryNorth Scotland, StorageNew stage added (50 MW from 31 Oct 2024)
- Rothienorman BatteryNorth Scotland, StorageAdded to the registerNew
- Rothienorman Sync CompNorth Scotland, OtherCustomer changed from WP Grid Services 8 Limited to ROTHIENORMAN GRID SERVICES LIMITED
- Rothienorman Sync CompNorth Scotland, OtherCustomer changed from ROTHIENORMAN GRID SERVICES LIMITED to WP Grid Services 8 Limited
- Rothienorman Sync CompNorth Scotland, OtherStatus changed from Awaiting Consents to Consents Approved
- Rothienorman Sync CompNorth Scotland, OtherCustomer changed from WP GRID SERVICES 8 LIMITED to ROTHIENORMAN GRID SERVICES LIMITED
- Rothienorman Sync CompNorth Scotland, OtherStatus changed from Scoping to Awaiting Consents
- Rothienorman Flexpower Synchronous CompensationNorth Scotland, OtherAdded to the registerNew
- Rothienorman Sync CompNorth Scotland, OtherAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?