QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / North Scotland

Rothienorman Sync Comp

ROTHIENORMAN GRID SERVICES LIMITED at Rothienorman 400kV Substation

Connection date
Connected
Gate
Not stated
Status
Built
Technology
Reactive compensation
Total capacity
0 MW
Connected now
0 MW
Still to connect
0 MW
Transmission owner
SSEN Transmission (SHET)
Agreement type
Direct Connection
Region
North Scotland
Project number
PRO-001445
In the register since
November 2021

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 31 Jan 2025 register
    Connection date removed (was 31 Oct 2024)
  • 31 Jan 2025 register
    Status changed from Consents Approved to Built
  • 29 Oct 2024 register
    Connection date moved from 31 Mar 2024 to 31 Oct 2024 (+7 months)
  • 23 Dec 2022 register
    Substation name updated in the register (from Rothienorman 400kV to Rothienorman 400kV Substation)
  • 29 Jul 2022 register
    Customer changed from WP Grid Services 8 Limited to ROTHIENORMAN GRID SERVICES LIMITED
  • 30 Jun 2022 register
    Customer changed from ROTHIENORMAN GRID SERVICES LIMITED to WP Grid Services 8 Limited
  • 30 Jun 2022 register
    Status changed from Awaiting Consents to Consents Approved
  • 31 May 2022 register
    Customer changed from WP GRID SERVICES 8 LIMITED to ROTHIENORMAN GRID SERVICES LIMITED
  • 31 Dec 2021 register
    Status changed from Scoping to Awaiting Consents
  • 30 Nov 2021 register
    Added to the register

Also at Rothienorman 400kV Substation

Substation view

1 other project, 500 MW still to connect at this substation in total.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO