Rhigos 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Nant Aman | NANT AMAN ENERGY PARK LIMITED | Onshore wind | 143 | 13 Dec 2030 | Gate 1 | Scoping |
| Tarenni | TARENNI ENERGY PARK LIMITED | Onshore wind | 188 | 13 Dec 2030 −1 mo | Gate 1 | Scoping |
| East Pit | CS UK HOLDINGS III LIMITED | Storage with solar or wind | 750 | 15 Oct 2037 | Gate 1 | Scoping |
| Hirwaun Power Station | HIRWAUN POWER LIMITED | Thermal (gas, biomass, waste) | 0 | Connected | Not stated | Built |
| Pen Y Cymoedd Wind Farm | PEN Y CYMOEDD WIND FARM LIMITED | Onshore wind | 0 | Connected | Not stated | Built |
Left the register since January 2021: Rhigos BESS (500 MW).
Recent changes
- TarenniEngland and Wales, Onshore windConnection date moved from 31 Dec 2030 to 13 Dec 2030 (−1 month)−1 mo
- TarenniEngland and Wales, Onshore windMarked as Gate 1
- Nant AmanEngland and Wales, Onshore windMarked as Gate 1
- East PitEngland and Wales, Storage with solar or windMarked as Gate 1
- Hirwaun Power StationEngland and Wales, Thermal (gas, biomass, waste)299 MW now connectedConnected
- Hirwaun Power StationEngland and Wales, Thermal (gas, biomass, waste)Status changed from Under Construction/Commissioning to Built
- TarenniEngland and Wales, Onshore windConnection date moved from 1 Oct 2028 to 31 Dec 2030 (+27 months)+27 mo
- Nant AmanEngland and Wales, Onshore windConnection date moved from 1 Oct 2028 to 13 Dec 2030 (+26 months)+26 mo
- Rhigos BESSEngland and Wales, StorageLeft the register (500 MW from 31 Oct 2037)500 MW
- Rhigos BESSEngland and Wales, StorageAdded to the registerNew
- East PitEngland and Wales, Storage with solar or windConnection point changed from East Pit New LILO 400kV substation to Rhigos 400kV Substation
- East PitEngland and Wales, Storage with solar or windAdded to the registerNew
- Hirwaun Power StationEngland and Wales, Thermal (gas, biomass, waste)Substation name updated in the register (from Rhigos GSP to Rhigos 400kV Substation)
- Nant AmanEngland and Wales, Onshore windSubstation name updated in the register (from Rhigos GSP to Rhigos 400kV Substation)
- TarenniEngland and Wales, Onshore windSubstation name updated in the register (from Rhigos GSP to Rhigos 400kV Substation)
- Hirwaun Power StationEngland and Wales, Thermal (gas, biomass, waste)Status changed from Consents Approved to Under Construction/Commissioning
- Hirwaun Power StationEngland and Wales, Thermal (gas, biomass, waste)Substation name updated in the register (from Rhigos to Rhigos GSP)
- Nant AmanEngland and Wales, Onshore windSubstation name updated in the register (from Rhigos to Rhigos GSP)
- Pen Y Cymoedd Wind FarmEngland and Wales, Onshore windSubstation name updated in the register (from Rhigos 400kV to Rhigos 400kV Substation)
- TarenniEngland and Wales, Onshore windSubstation name updated in the register (from Rhigos to Rhigos GSP)
- Nant AmanEngland and Wales, Onshore windAdded to the registerNew
- Hirwaun Power StationEngland and Wales, Thermal (gas, biomass, waste)Connection date moved from 10 Jul 2021 to 30 Sep 2023 (+27 months)+27 mo
- TarenniEngland and Wales, Onshore windAdded to the registerNew
- Hirwaun Power StationEngland and Wales, Thermal (gas, biomass, waste)Connection date moved from 7 Oct 2021 to 10 Jul 2021 (−3 months)−3 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose