Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / Substation

Penwortham 400kV Substation

England and Wales, National Grid Electricity Transmission

6projects in the register
2.7 GWstill to connect
57 MWof that with Gate 2 offers
20 MWconnected now

The queue at this substation

ProjectCustomerTechnologyQueued MWConnection dateGateStatus
Penwortham BESSPENWORTHAM (BES) LTDStorage5730 Oct 2028 +12 moGate 2Consents Approved
Morecambe Offshore Wind FarmMORECAMBE OFFSHORE WINDFARM LTDOffshore wind48030 Jun 2029Not statedScoping
Morgan Offshore Wind FarmMorgan Offshore Wind LimitedOffshore wind1,50030 Nov 2029Not statedScoping
Penwortham BESSCSE28 LIMITEDStorage571 Jun 2031Gate 1Scoping
Penwortham Green Energy CentrePenwortham NG LimitedStorage with solar or wind60030 Oct 2035Gate 1Awaiting Consents
Bispham BEGACONRAD (BISPHAM) LIMITEDThermal (gas, biomass, waste)0ConnectedNot statedBuilt

Recent changes

  • Penwortham BESSEngland and Wales, StorageStatus changed from Scoping to Consents Approved
  • Bispham BEGAEngland and Wales, Thermal (gas, biomass, waste)Added to the registerNew
  • Penwortham BESSEngland and Wales, StorageConnection date moved from 30 Oct 2027 to 30 Oct 2028 (+12 months)+12 mo
  • Penwortham BESSEngland and Wales, StorageGiven a Gate 2 connection offerGate 2
  • Penwortham Green Energy CentreEngland and Wales, Storage with solar or windCustomer changed from PENWORTHAM GREEN ENERGY LIMITED to Penwortham NG Limited
  • Penwortham BESSEngland and Wales, StorageMarked as Gate 1
  • Penwortham Green Energy CentreEngland and Wales, Storage with solar or windMarked as Gate 1
  • Penwortham BESSEngland and Wales, StorageStage removed (0 MW from 30 Oct 2037)
  • Penwortham Green Energy CentreEngland and Wales, Storage with solar or windRestructured from 4 stages (0 MW from 30 Oct 2035, 200 MW from 30 Oct 2035, 400 MW from 31 Oct 2035, 0 MW from 30 Oct 2037) to 1 stage (600 MW from 30 Oct 2035)
  • Morgan Offshore Wind FarmEngland and Wales, Offshore windStage removed (0 MW from 30 Oct 2032)
  • Morgan Offshore Wind FarmEngland and Wales, Offshore windStage removed (0 MW from 30 Dec 2033)
  • Morgan Offshore Wind FarmEngland and Wales, Offshore windNew stage added (0 MW from 30 Oct 2032)
  • Morgan Offshore Wind FarmEngland and Wales, Offshore windNew stage added (0 MW from 30 Dec 2033)
  • Penwortham BESSEngland and Wales, StorageRestructured from 1 stage (57 MW from 31 Oct 2024) to 2 stages (57 MW from 30 Oct 2027, 0 MW from 30 Oct 2037). First connection date +36 months+36 mo
  • Penwortham BESSEngland and Wales, StorageConnection date moved from 1 Jun 2027 to 1 Jun 2031 (+48 months)+48 mo
  • Penwortham Green Energy CentreEngland and Wales, Storage with solar or windStage 1: Connection date moved from 31 Oct 2026 to 31 Oct 2035 (+108 months)+108 mo
  • Penwortham Green Energy CentreEngland and Wales, Storage with solar or windStage 2: Capacity changed from 200 MW to 0 MW
  • Penwortham Green Energy CentreEngland and Wales, Storage with solar or windStage 2: Connection date moved from 31 Oct 2037 to 30 Oct 2035 (−24 months)−24 mo
  • Penwortham Green Energy CentreEngland and Wales, Storage with solar or windNew stage added (200 MW from 30 Oct 2035)
  • Penwortham Green Energy CentreEngland and Wales, Storage with solar or windNew stage added (0 MW from 30 Oct 2037)
  • Morecambe Offshore Wind FarmEngland and Wales, Offshore windCustomer changed from OFFSHORE WIND LIMITED to MORECAMBE OFFSHORE WINDFARM LTD
  • Penwortham Green Energy CentreEngland and Wales, Storage with solar or windStage 1: Technology changed from Storage, Solar to Demand, Storage, Solar
  • Penwortham Green Energy CentreEngland and Wales, Storage with solar or windStage 2: Technology changed from Storage, Solar to Demand, Storage, Solar
  • Penwortham Green Energy CentreEngland and Wales, Storage with solar or windStage 2: Connection date moved from 31 Oct 2036 to 31 Oct 2037 (+12 months)+12 mo
  • Morgan Offshore Wind FarmEngland and Wales, Offshore windConnection point changed from Wylfa 400kV Substation to Penwortham 400kV Substation
  • Morgan Offshore Wind FarmEngland and Wales, Offshore windConnection date moved from 1 Apr 2033 to 30 Nov 2029 (−40 months)−40 mo
  • Morecambe Offshore Wind FarmEngland and Wales, Offshore windConnection point changed from Wylfa 400kV Substation to Penwortham 400kV Substation
  • Morecambe Offshore Wind FarmEngland and Wales, Offshore windConnection date moved from 1 Apr 2033 to 30 Jun 2029 (−45 months)−45 mo
  • Morgan Offshore Wind FarmEngland and Wales, Offshore windRenamed from Elizabeth Yellow One
  • Morgan Offshore Wind FarmEngland and Wales, Offshore windCustomer changed from BP ALTERNATIVE ENERGY INVESTMENTS LIMITED to Morgan Offshore Wind Limited
  • Penwortham Green Energy CentreEngland and Wales, Storage with solar or windRestructured from 1 stage (400 MW from 31 Oct 2026) to 2 stages (400 MW from 31 Oct 2026, 200 MW from 31 Oct 2036)
  • Penwortham BESSEngland and Wales, StorageAdded to the registerNew
  • Penwortham BESSEngland and Wales, StorageCustomer changed from SHAW-ENERGI LTD to Penwortham (BES) Ltd
  • Morecambe Offshore Wind FarmEngland and Wales, Offshore windSubstation name updated in the register (from Wylfa 400kV to Wylfa 400kV Substation)
  • Morgan Offshore Wind FarmEngland and Wales, Offshore windSubstation name updated in the register (from Wylfa 400kV to Wylfa 400kV Substation)
  • Penwortham BESSEngland and Wales, StorageCustomer changed from Penwortham (BES) Ltd to SHAW-ENERGI LTD
  • Penwortham BESSEngland and Wales, StorageCustomer changed from SHAW-ENERGI LTD to Penwortham (BES) Ltd
  • Penwortham Green Energy CentreEngland and Wales, Storage with solar or windConnection date moved from 30 Oct 2026 to 31 Oct 2026 (1 day later)
  • Penwortham BESSEngland and Wales, StorageConnection point changed from Penwortham to Penwortham 400kV Substation
  • Penwortham Green Energy CentreEngland and Wales, Storage with solar or windConnection point changed from Penwortham to Penwortham GSP
  • Penwortham BESSEngland and Wales, StorageAdded to the registerNew
  • Morgan Offshore Wind FarmEngland and Wales, Offshore windRenamed from Elizabeth Yellow 2nd Project
  • Morgan Offshore Wind FarmEngland and Wales, Offshore windAdded to the registerNew
  • Penwortham Green Energy CentreEngland and Wales, Storage with solar or windAdded to the registerNew
  • Morecambe Offshore Wind FarmEngland and Wales, Offshore windAdded to the registerNew
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO