Penwortham 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Penwortham BESS | PENWORTHAM (BES) LTD | Storage | 57 | 30 Oct 2028 +12 mo | Gate 2 | Consents Approved |
| Morecambe Offshore Wind Farm | MORECAMBE OFFSHORE WINDFARM LTD | Offshore wind | 480 | 30 Jun 2029 | Not stated | Scoping |
| Morgan Offshore Wind Farm | Morgan Offshore Wind Limited | Offshore wind | 1,500 | 30 Nov 2029 | Not stated | Scoping |
| Penwortham BESS | CSE28 LIMITED | Storage | 57 | 1 Jun 2031 | Gate 1 | Scoping |
| Penwortham Green Energy Centre | Penwortham NG Limited | Storage with solar or wind | 600 | 30 Oct 2035 | Gate 1 | Awaiting Consents |
| Bispham BEGA | CONRAD (BISPHAM) LIMITED | Thermal (gas, biomass, waste) | 0 | Connected | Not stated | Built |
Recent changes
- Penwortham BESSEngland and Wales, StorageStatus changed from Scoping to Consents Approved
- Bispham BEGAEngland and Wales, Thermal (gas, biomass, waste)Added to the registerNew
- Penwortham BESSEngland and Wales, StorageConnection date moved from 30 Oct 2027 to 30 Oct 2028 (+12 months)+12 mo
- Penwortham BESSEngland and Wales, StorageGiven a Gate 2 connection offerGate 2
- Penwortham Green Energy CentreEngland and Wales, Storage with solar or windCustomer changed from PENWORTHAM GREEN ENERGY LIMITED to Penwortham NG Limited
- Penwortham BESSEngland and Wales, StorageMarked as Gate 1
- Penwortham Green Energy CentreEngland and Wales, Storage with solar or windMarked as Gate 1
- Penwortham BESSEngland and Wales, StorageStage removed (0 MW from 30 Oct 2037)
- Penwortham Green Energy CentreEngland and Wales, Storage with solar or windRestructured from 4 stages (0 MW from 30 Oct 2035, 200 MW from 30 Oct 2035, 400 MW from 31 Oct 2035, 0 MW from 30 Oct 2037) to 1 stage (600 MW from 30 Oct 2035)
- Morgan Offshore Wind FarmEngland and Wales, Offshore windStage removed (0 MW from 30 Oct 2032)
- Morgan Offshore Wind FarmEngland and Wales, Offshore windStage removed (0 MW from 30 Dec 2033)
- Morgan Offshore Wind FarmEngland and Wales, Offshore windNew stage added (0 MW from 30 Oct 2032)
- Morgan Offshore Wind FarmEngland and Wales, Offshore windNew stage added (0 MW from 30 Dec 2033)
- Penwortham BESSEngland and Wales, StorageRestructured from 1 stage (57 MW from 31 Oct 2024) to 2 stages (57 MW from 30 Oct 2027, 0 MW from 30 Oct 2037). First connection date +36 months+36 mo
- Penwortham BESSEngland and Wales, StorageConnection date moved from 1 Jun 2027 to 1 Jun 2031 (+48 months)+48 mo
- Penwortham Green Energy CentreEngland and Wales, Storage with solar or windStage 1: Connection date moved from 31 Oct 2026 to 31 Oct 2035 (+108 months)+108 mo
- Penwortham Green Energy CentreEngland and Wales, Storage with solar or windStage 2: Capacity changed from 200 MW to 0 MW
- Penwortham Green Energy CentreEngland and Wales, Storage with solar or windStage 2: Connection date moved from 31 Oct 2037 to 30 Oct 2035 (−24 months)−24 mo
- Penwortham Green Energy CentreEngland and Wales, Storage with solar or windNew stage added (200 MW from 30 Oct 2035)
- Penwortham Green Energy CentreEngland and Wales, Storage with solar or windNew stage added (0 MW from 30 Oct 2037)
- Morecambe Offshore Wind FarmEngland and Wales, Offshore windCustomer changed from OFFSHORE WIND LIMITED to MORECAMBE OFFSHORE WINDFARM LTD
- Penwortham Green Energy CentreEngland and Wales, Storage with solar or windStage 1: Technology changed from Storage, Solar to Demand, Storage, Solar
- Penwortham Green Energy CentreEngland and Wales, Storage with solar or windStage 2: Technology changed from Storage, Solar to Demand, Storage, Solar
- Penwortham Green Energy CentreEngland and Wales, Storage with solar or windStage 2: Connection date moved from 31 Oct 2036 to 31 Oct 2037 (+12 months)+12 mo
- Morgan Offshore Wind FarmEngland and Wales, Offshore windConnection point changed from Wylfa 400kV Substation to Penwortham 400kV Substation
- Morgan Offshore Wind FarmEngland and Wales, Offshore windConnection date moved from 1 Apr 2033 to 30 Nov 2029 (−40 months)−40 mo
- Morecambe Offshore Wind FarmEngland and Wales, Offshore windConnection point changed from Wylfa 400kV Substation to Penwortham 400kV Substation
- Morecambe Offshore Wind FarmEngland and Wales, Offshore windConnection date moved from 1 Apr 2033 to 30 Jun 2029 (−45 months)−45 mo
- Morgan Offshore Wind FarmEngland and Wales, Offshore windRenamed from Elizabeth Yellow One
- Morgan Offshore Wind FarmEngland and Wales, Offshore windCustomer changed from BP ALTERNATIVE ENERGY INVESTMENTS LIMITED to Morgan Offshore Wind Limited
- Penwortham Green Energy CentreEngland and Wales, Storage with solar or windRestructured from 1 stage (400 MW from 31 Oct 2026) to 2 stages (400 MW from 31 Oct 2026, 200 MW from 31 Oct 2036)
- Penwortham BESSEngland and Wales, StorageAdded to the registerNew
- Penwortham BESSEngland and Wales, StorageCustomer changed from SHAW-ENERGI LTD to Penwortham (BES) Ltd
- Morecambe Offshore Wind FarmEngland and Wales, Offshore windSubstation name updated in the register (from Wylfa 400kV to Wylfa 400kV Substation)
- Morgan Offshore Wind FarmEngland and Wales, Offshore windSubstation name updated in the register (from Wylfa 400kV to Wylfa 400kV Substation)
- Penwortham BESSEngland and Wales, StorageCustomer changed from Penwortham (BES) Ltd to SHAW-ENERGI LTD
- Penwortham BESSEngland and Wales, StorageCustomer changed from SHAW-ENERGI LTD to Penwortham (BES) Ltd
- Penwortham Green Energy CentreEngland and Wales, Storage with solar or windConnection date moved from 30 Oct 2026 to 31 Oct 2026 (1 day later)
- Penwortham BESSEngland and Wales, StorageConnection point changed from Penwortham to Penwortham 400kV Substation
- Penwortham Green Energy CentreEngland and Wales, Storage with solar or windConnection point changed from Penwortham to Penwortham GSP
- Penwortham BESSEngland and Wales, StorageAdded to the registerNew
- Morgan Offshore Wind FarmEngland and Wales, Offshore windRenamed from Elizabeth Yellow 2nd Project
- Morgan Offshore Wind FarmEngland and Wales, Offshore windAdded to the registerNew
- Penwortham Green Energy CentreEngland and Wales, Storage with solar or windAdded to the registerNew
- Morecambe Offshore Wind FarmEngland and Wales, Offshore windAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?