Penwortham NG Limited
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Penwortham Green Energy Centre | Penwortham 400kV Substation | Storage with solar or wind | 600 | 30 Oct 2035 | Gate 1 | Awaiting Consents |
Recent changes
- Penwortham Green Energy CentreEngland and Wales, Storage with solar or windCustomer changed from PENWORTHAM GREEN ENERGY LIMITED to Penwortham NG Limited
- Penwortham Green Energy CentreEngland and Wales, Storage with solar or windMarked as Gate 1
- Penwortham Green Energy CentreEngland and Wales, Storage with solar or windRestructured from 4 stages (0 MW from 30 Oct 2035, 200 MW from 30 Oct 2035, 400 MW from 31 Oct 2035, 0 MW from 30 Oct 2037) to 1 stage (600 MW from 30 Oct 2035)
- Penwortham Green Energy CentreEngland and Wales, Storage with solar or windStage 1: Connection date moved from 31 Oct 2026 to 31 Oct 2035 (+108 months)+108 mo
- Penwortham Green Energy CentreEngland and Wales, Storage with solar or windStage 2: Capacity changed from 200 MW to 0 MW
- Penwortham Green Energy CentreEngland and Wales, Storage with solar or windStage 2: Connection date moved from 31 Oct 2037 to 30 Oct 2035 (−24 months)−24 mo
- Penwortham Green Energy CentreEngland and Wales, Storage with solar or windNew stage added (200 MW from 30 Oct 2035)
- Penwortham Green Energy CentreEngland and Wales, Storage with solar or windNew stage added (0 MW from 30 Oct 2037)
- Penwortham Green Energy CentreEngland and Wales, Storage with solar or windStage 1: Technology changed from Storage, Solar to Demand, Storage, Solar
- Penwortham Green Energy CentreEngland and Wales, Storage with solar or windStage 2: Technology changed from Storage, Solar to Demand, Storage, Solar
- Penwortham Green Energy CentreEngland and Wales, Storage with solar or windStage 2: Connection date moved from 31 Oct 2036 to 31 Oct 2037 (+12 months)+12 mo
- Penwortham Green Energy CentreEngland and Wales, Storage with solar or windRestructured from 1 stage (400 MW from 31 Oct 2026) to 2 stages (400 MW from 31 Oct 2026, 200 MW from 31 Oct 2036)
- Penwortham Green Energy CentreEngland and Wales, Storage with solar or windConnection date moved from 30 Oct 2026 to 31 Oct 2026 (1 day later)
- Penwortham Green Energy CentreEngland and Wales, Storage with solar or windConnection point changed from Penwortham to Penwortham GSP
- Penwortham Green Energy CentreEngland and Wales, Storage with solar or windAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?