Pelham 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Pelham Farm 2 | 548 UK INVESTMENT HOLDINGS LIMITED | Storage with solar or wind | 700 | 31 Oct 2032 | Gate 1 | Scoping |
| Pelham GEC (Ethos Green) | PELHAM GREEN ENERGY CENTRE LTD | Storage | 480 | 31 May 2035 | Gate 1 | Awaiting Consents |
Left the register since January 2021: Pelham Farm (700 MW).
Recent changes
- Pelham Farm 2England and Wales, Storage with solar or windAdded to the registerNew
- Pelham GEC (Ethos Green)England and Wales, StorageMarked as Gate 1
- Pelham GEC (Ethos Green)England and Wales, StorageTechnology changed from Demand, Storage, Reactive compensation to Storage
- Pelham Farm 2England and Wales, Storage with solar or windLeft the register (700 MW from 31 Oct 2032)700 MW
- Pelham GEC (Ethos Green)England and Wales, StorageTechnology changed from Demand, Storage to Demand, Storage, Reactive compensation
- Pelham GEC (Ethos Green)England and Wales, StorageTechnology changed from Demand, Storage, Solar, Reactive compensation to Demand, Storage
- Pelham Farm 2England and Wales, Storage with solar or windAdded to the registerNew
- Pelham FarmEngland and Wales, Storage with solar or windLeft the register (700 MW from 31 Oct 2032)700 MW
- Pelham GEC (Ethos Green)England and Wales, StorageRenamed from Pelham GEC
- Pelham GEC (Ethos Green)England and Wales, StorageAdded to the registerNew
- Pelham FarmEngland and Wales, Storage with solar or windAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?