Transmission / Projects / England and Wales
Connection date
Left 22 May 2026
Gate
Not stated
Status
Scoping
Technology
Storage + Solar
Total capacity
700 MW
Connected now
0 MW
Still to connect
700 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Direct Connection
Region
England and Wales
Project number
PRO-002742
In the register since
June 2024

Change history

Every change to this project across 146 registers from 29 Jan 2021 to 20 Oct 2026.

  • 22 May 2026 register
    Left the register (700 MW from 31 Oct 2032)
  • 28 Jun 2024 register
    Added to the register

Also at Pelham 400kV Substation

Substation view

1 other project, 480 MW still to connect at this substation in total.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO