Overhill 132kV Substation
South Scotland, SP Energy Networks
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Overhill Wind Farm | ENERGYFARM UK OVERHILL LLP | Onshore wind | 50 | 6 Jun 2029 | Not stated | Consents Approved |
Recent changes
- Overhill Wind FarmSouth Scotland, Onshore windConnection date moved from 30 Jun 2027 to 6 Jun 2029 (+23 months)+23 mo
- Overhill Wind FarmSouth Scotland, Onshore windConnection point changed from Overhill WF 132kV Substation to Overhill 132kV Substation
- Overhill Wind FarmSouth Scotland, Onshore windConnection date moved from 26 Aug 2027 to 30 Jun 2027 (−2 months)−2 mo
- Overhill Wind FarmSouth Scotland, Onshore windConnection date moved from 8 Jul 2026 to 26 Aug 2027 (+14 months)+14 mo
- Overhill Wind FarmSouth Scotland, Onshore windSubstation name updated in the register (from Overhill WF 132kV to Overhill WF 132kV Substation)
- Overhill Wind FarmSouth Scotland, Onshore windCapacity changed from 48 MW to 50 MW
- Overhill Wind FarmSouth Scotland, Onshore windConnection date moved from 8 Jul 2025 to 8 Jul 2026 (+12 months)+12 mo
- Overhill Wind FarmSouth Scotland, Onshore windConnection date moved from 8 Sep 2023 to 8 Jul 2025 (+22 months)+22 mo
- Overhill Wind FarmSouth Scotland, Onshore windConnection date moved from 9 Aug 2023 to 8 Sep 2023 (+1 month)+1 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?