QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / South Scotland

Overhill Wind Farm

ENERGYFARM UK OVERHILL LLP at Overhill 132kV Substation

Connection date
6 Jun 2029
Gate
Not stated
Status
Consents Approved
Technology
Onshore wind
Total capacity
50 MW
Connected now
0 MW
Still to connect
50 MW
Transmission owner
SP Energy Networks (SPT)
Agreement type
Direct Connection
Region
South Scotland
Project number
PRO-000472
In the register since
January 2021 or earlier

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 28 Mar 2025 register
    Connection date moved from 30 Jun 2027 to 6 Jun 2029 (+23 months)
  • 28 Feb 2025 register
    Connection point changed from Overhill WF 132kV Substation to Overhill 132kV Substation
  • 30 Jan 2024 register
    Connection date moved from 26 Aug 2027 to 30 Jun 2027 (−2 months)
  • 31 Jan 2023 register
    Connection date moved from 8 Jul 2026 to 26 Aug 2027 (+14 months)
  • 23 Dec 2022 register
    Substation name updated in the register (from Overhill WF 132kV to Overhill WF 132kV Substation)
  • 25 Feb 2022 register
    Capacity changed from 48 MW to 50 MW
  • 25 Feb 2022 register
    Connection date moved from 8 Jul 2025 to 8 Jul 2026 (+12 months)
  • 30 Apr 2021 register
    Connection date moved from 8 Sep 2023 to 8 Jul 2025 (+22 months)
  • 26 Feb 2021 register
    Connection date moved from 9 Aug 2023 to 8 Sep 2023 (+1 month)

Also at Overhill 132kV Substation

Substation view

No other projects in the register at this connection point.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO