Norwich GSP
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Norwich Yare | ASHGREEN ENERGYFARM LIMITED | Storage with solar or wind | 49.5 | 18 Dec 2025 Past date | Not stated | Consents Approved |
Recent changes
- Norwich YareEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2024 to 18 Dec 2025 (+14 months)+14 mo
- Norwich YareEngland and Wales, Storage with solar or windRenamed from Norwich
- Norwich YareEngland and Wales, Storage with solar or windTechnology changed from Gas (CCGT) to Storage, Solar
- Norwich YareEngland and Wales, Storage with solar or windCustomer changed from YARE POWER LIMITED to ASH GREEN ENERGY FARM LIMITED
- Norwich YareEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2023 to 31 Oct 2024 (+12 months)+12 mo
- Norwich YareEngland and Wales, Storage with solar or windSubstation name updated in the register (from Norwich to Norwich GSP)
- Norwich YareEngland and Wales, Storage with solar or windConnection date moved from 30 Jun 2024 to 31 Oct 2023 (−8 months)−8 mo
- Norwich YareEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2023 to 30 Jun 2024 (+8 months)+8 mo
- Norwich YareEngland and Wales, Storage with solar or windConnection date moved from 1 Jul 2022 to 31 Oct 2023 (+16 months)+16 mo
- Norwich YareEngland and Wales, Storage with solar or windConnection date moved from 7 Jan 2022 to 1 Jul 2022 (+6 months)+6 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?