Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / Substation

North Wales connection Node A 400kV Substation

England and Wales, National Grid Electricity Transmission

4projects in the register
1.3 GWstill to connect
0 MWof that with Gate 2 offers
0 MWconnected now

The queue at this substation

ProjectCustomerTechnologyQueued MWConnection dateGateStatus
Gwynt Alwen WFBWLCH GWYN WIND FARM LIMITEDStorage with solar or wind10830 Jun 2030Not statedScoping
Foel Fach Wind FarmFOEL FACH WIND FARM LIMITEDStorage with solar or wind79.231 Oct 2037Not statedScoping
NatPower Gwyddelwern Green Energy ParkGWYDDELWERN ENERGY LIMITEDStorage1,00031 Oct 2037Gate 1Scoping
Orddu Energy ParkOrddu Energy Park LimitedOnshore wind85.831 Oct 2037Not statedScoping

Recent changes

  • NatPower Gwyddelwern Green Energy ParkEngland and Wales, StorageCustomer changed from NP SPV31 Limited to GWYDDELWERN ENERGY LIMITED
  • NatPower Gwyddelwern Green Energy ParkEngland and Wales, StorageMarked as Gate 1
  • Orddu Energy ParkEngland and Wales, Onshore windConnection point changed from Gwyddelwern 400kV Substation to North Wales connection Node A 400kV Substation
  • Gwynt Alwen WFEngland and Wales, Storage with solar or windCustomer changed from WIND 2 LIMITED to BWLCH GWYN WIND FARM LIMITED
  • Gwynt Alwen WFEngland and Wales, Storage with solar or windRestructured from 1 stage (108 MW from 30 Apr 2027) to 2 stages (108 MW from 30 Jun 2030, 0 MW from 31 Oct 2032). First connection date +38 months+38 mo
  • Foel Fach Wind FarmEngland and Wales, Storage with solar or windAdded to the registerNew
  • Gwynt Alwen WFEngland and Wales, Storage with solar or windConnection point changed from Gwyddelwern 400kV Substation to North Wales connection Node A 400kV Substation
  • Gwynt Alwen WFEngland and Wales, Storage with solar or windTechnology changed from Onshore wind to Storage, Onshore wind
  • NatPower Gwyddelwern Green Energy ParkEngland and Wales, StorageAdded to the registerNew
  • Gwynt Alwen WFEngland and Wales, Storage with solar or windConnection point changed from Trawsfynydd GSP to Gwyddelwern 400kV Substation
  • Orddu Energy ParkEngland and Wales, Onshore windAdded to the registerNew
  • Gwynt Alwen WFEngland and Wales, Storage with solar or windSubstation name updated in the register (from Trawsfynydd to Trawsfynydd GSP)
  • Gwynt Alwen WFEngland and Wales, Storage with solar or windCustomer changed from Wind 2 to Wind 2 Limited
  • Gwynt Alwen WFEngland and Wales, Storage with solar or windAdded to the registerNew
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO