Projects / England and Wales
- Connection date
- 30 Jun 2030
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage + Solar + Reactive compensation + Onshore wind
- Total capacity
- 108 MW
- Connected now
- 0 MW
- Still to connect
- 108 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001545
- Tracked since
- 14 Aug 2026
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 0 | 108 | 108 | 30 Jun 2030 | Not stated | Scoping |
| 2 | 0 | 0 | 108 | 31 Oct 2032 | Not stated | Scoping |
Change history
Every change to this project across 9 registers from 14 Aug 2026 to 21 Sep 2026.
No changes since 14 Aug 2026. Follow this project to see the next one on your watchlist.
Also queued at North Wales connection Node A 400kV Substation
Substation view3 other projects, 1.3 GW still to connect at this substation in total.