North Kyle 132/33kV substation
South Scotland, SP Energy Networks
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| North Kyle New Cumnock | NORTH KYLE WIND FARM LIMITED | Onshore wind | 0 | Connected | Gate 2 | Built |
Recent changes
- North Kyle New CumnockSouth Scotland, Onshore windRestructured from 2 stages (79 MW connected, 79 MW connected + 133 MW from 4 Feb 2026) to 1 stage (212 MW connected)
- North Kyle New CumnockSouth Scotland, Onshore windRestructured from 1 stage (212 MW connected) to 2 stages (79 MW connected, 79 MW connected + 133 MW from 4 Feb 2026)
- North Kyle New CumnockSouth Scotland, Onshore windConnection point changed from New Cumnock 275/132kV Substation to North Kyle 132/33kV substation
- North Kyle New CumnockSouth Scotland, Onshore windConnection date removed (was 4 Feb 2026)
- North Kyle New CumnockSouth Scotland, Onshore windGate marking removed (was Gate 2)
- North Kyle New CumnockSouth Scotland, Onshore windConnection date set to 4 Feb 2026
- North Kyle New CumnockSouth Scotland, Onshore windTechnology changed from Storage, Onshore wind to Onshore wind
- North Kyle New CumnockSouth Scotland, Onshore windGiven a Gate 2 connection offerGate 2
- North Kyle New CumnockSouth Scotland, Onshore wind133 MW now connectedConnected
- North Kyle New CumnockSouth Scotland, Onshore windConnection date set to 30 May 2025
- North Kyle New CumnockSouth Scotland, Onshore windRestructured from 2 stages (133 MW from 30 May 2025, 79 MW connected) to 1 stage (79 MW connected + 133 MW)
- North Kyle New CumnockSouth Scotland, Onshore windStage 1: 79 MW now connectedConnected
- North Kyle New CumnockSouth Scotland, Onshore windStage 1: Status changed from Awaiting Consents to Built
- North Kyle New CumnockSouth Scotland, Onshore windStage 2: Connection date moved from 3 Apr 2028 to 30 May 2025 (−34 months)−34 mo
- North Kyle New CumnockSouth Scotland, Onshore windRestructured from 1 stage (212 MW from 30 Apr 2024) to 2 stages (79 MW from 18 Dec 2024, 133 MW from 3 Apr 2028). First connection date +8 months+8 mo
- North Kyle New CumnockSouth Scotland, Onshore windConnection point changed from New Cumnock 132kV Substation to New Cumnock 275/132kV
- North Kyle New CumnockSouth Scotland, Onshore windSubstation name updated in the register (from New Cumnock 132kV to New Cumnock 132kV Substation)
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?