Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / South Scotland

North Kyle New Cumnock

NORTH KYLE WIND FARM LIMITED at North Kyle 132/33kV substation

Connection date
Connected
Gate
Gate 2
Status
Built
Planning consent
Granted 30 Jun 2021
Scottish Government (S36), reference ECU00001950 · Source: REPD
Contract for Difference
Allocation Round 4
Technology
Onshore wind
Total capacity
212 MW
Connected now
212 MW
Still to connect
0 MW
Transmission owner
SP Energy Networks (SPT)
Agreement type
Direct Connection
Region
South Scotland
Project number
PRO-000474
In the register since
January 2021 or earlier

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 11 Sep 2026 register
    Restructured from 2 stages (79 MW connected, 79 MW connected + 133 MW from 4 Feb 2026) to 1 stage (212 MW connected)
  • 4 Sep 2026 register
    Restructured from 1 stage (212 MW connected) to 2 stages (79 MW connected, 79 MW connected + 133 MW from 4 Feb 2026)
  • 21 Jul 2026 register
    Connection point changed from New Cumnock 275/132kV Substation to North Kyle 132/33kV substation
  • 7 Jul 2026 register
    Connection date removed (was 4 Feb 2026)
  • 7 Jul 2026 register
    Gate marking removed (was Gate 2)
  • 3 Jul 2026 register
    Connection date set to 4 Feb 2026
  • 3 Jul 2026 register
    Technology changed from Storage, Onshore wind to Onshore wind
  • 3 Jul 2026 register
    Given a Gate 2 connection offer
  • 26 Jun 2026 register
    133 MW now connected
  • 21 Nov 2025 register
    Connection date set to 30 May 2025
  • 31 Oct 2025 register
    Restructured from 2 stages (133 MW from 30 May 2025, 79 MW connected) to 1 stage (79 MW connected + 133 MW)
  • 29 Jul 2025 register
    Stage 1: 79 MW now connected
  • 29 Jul 2025 register
    Stage 1: Status changed from Awaiting Consents to Built
  • 29 Apr 2025 register
    Stage 2: Connection date moved from 3 Apr 2028 to 30 May 2025 (−34 months)
  • 28 Feb 2025 register
    Restructured from 1 stage (212 MW from 30 Apr 2024) to 2 stages (79 MW from 18 Dec 2024, 133 MW from 3 Apr 2028). First connection date +8 months
  • 27 Sep 2024 register
    Connection point changed from New Cumnock 132kV Substation to New Cumnock 275/132kV
  • 23 Dec 2022 register
    Substation name updated in the register (from New Cumnock 132kV to New Cumnock 132kV Substation)

Also at North Kyle 132/33kV substation

Substation view

No other projects in the register at this connection point.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO

Planning consent

The planning decision or stage for this project, from DESNZ’s Renewable Energy Planning Database (REPD), July 2026 edition, with the planning authority and its reference. QueueWatch matched the project to that record. NESO’s status can lag behind planning decisions, so the two may differ.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.

Contract for Difference

The Contracts for Difference allocation round for this project, from DESNZ’s Renewable Energy Planning Database (REPD), July 2026 edition. QueueWatch matched the project to that record.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.