New Cumnock 275/132kV
South Scotland, SP Energy Networks
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| New Cumnock BESS | NEW CUMNOCK BESS LTD | Storage with solar or wind | 450 | 30 Oct 2033 | Gate 1 | Scoping |
| South Kyle Wind Farm | SOUTH KYLE WIND FARM LIMITED | Onshore wind | 0 | Connected | Not stated | Built |
Recent changes
- New Cumnock BESSSouth Scotland, Storage with solar or windMarked as Gate 1
- New Cumnock BESSSouth Scotland, Storage with solar or windConnection date moved from 30 Oct 2030 to 30 Oct 2033 (+36 months)+36 mo
- South Kyle Wind FarmSouth Scotland, Onshore windConnection point changed from New Cumnock 132kV Substation to New Cumnock 275/132kV
- New Cumnock BESSSouth Scotland, Storage with solar or windAdded to the registerNew
- South Kyle Wind FarmSouth Scotland, Onshore windSubstation name updated in the register (from New Cumnock 132kV to New Cumnock 132kV Substation)
- South Kyle Wind FarmSouth Scotland, Onshore wind235 MW now connectedConnected
- South Kyle Wind FarmSouth Scotland, Onshore windStatus changed from Consents Approved to Built
- South Kyle Wind FarmSouth Scotland, Onshore windRenamed from South Kyle
- South Kyle Wind FarmSouth Scotland, Onshore windStage removed (−41 MW from 30 Apr 2022)
- South Kyle Wind FarmSouth Scotland, Onshore windStage removed (−29 MW from 30 Aug 2022)
- South Kyle Wind FarmSouth Scotland, Onshore windStage removed (70 MW from 30 Oct 2022)
- South Kyle Wind FarmSouth Scotland, Onshore windStage 1: Connection date moved from 4 Jan 2022 to 1 Apr 2022 (+3 months)+3 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?