South Kyle Wind Farm
- Connection date
- Connected
- Gate
- Not stated
- Status
- Built
- Planning consent
- Granted on appeal 30 Jun 2017
Scottish Government (S36), reference EC00003109 · Source: REPD - Technology
- Onshore wind
- Total capacity
- 235 MW
- Connected now
- 235 MW
- Still to connect
- 0 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-000137
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 27 Sep 2024 registerConnection point changed from New Cumnock 132kV Substation to New Cumnock 275/132kV
- 23 Dec 2022 registerSubstation name updated in the register (from New Cumnock 132kV to New Cumnock 132kV Substation)
- 30 Jun 2022 register235 MW now connected
- 30 Jun 2022 registerStatus changed from Consents Approved to Built
- 30 Mar 2022 registerRenamed from South Kyle
- 29 Jun 2021 registerStage removed (−41 MW from 30 Apr 2022)
- 29 Jun 2021 registerStage removed (−29 MW from 30 Aug 2022)
- 29 Jun 2021 registerStage removed (70 MW from 30 Oct 2022)
- 26 Feb 2021 registerStage 1: Connection date moved from 4 Jan 2022 to 1 Apr 2022 (+3 months)
Also at New Cumnock 275/132kV
Substation view1 other project, 450 MW still to connect at this substation in total.