Lunanhead GSP
North Scotland, SSEN Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Montreathmont Moor Forest | Montreathmont Energy Centre Limited | Storage with solar or wind | 34.4 | 31 Oct 2026 Past date −35 mo | Gate 2 | Consents Approved |
Left the register since January 2021: Forfar Solar - DNO (27.8 MW).
Recent changes
- Montreathmont Moor ForestNorth Scotland, Storage with solar or windStatus changed from Scoping to Consents Approved
- Montreathmont Moor ForestNorth Scotland, Storage with solar or windConnection date moved from 8 Oct 2029 to 31 Oct 2026 (−35 months)−35 mo
- Montreathmont Moor ForestNorth Scotland, Storage with solar or windGiven a Gate 2 connection offerGate 2
- Montreathmont Moor ForestNorth Scotland, Storage with solar or windConnection date moved from 31 Oct 2025 to 8 Oct 2029 (+47 months)+47 mo
- Forfar Solar - DNONorth Scotland, SolarLeft the register (27.8 MW from 31 Oct 2025)27.8 MW
- Forfar Solar - DNONorth Scotland, SolarAdded to the registerNew
- Montreathmont Moor ForestNorth Scotland, Storage with solar or windAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?