Montreathmont Moor Forest
- Connection date
- 31 Oct 2026 −35 months since 9 Dec
- Gate
- Gate 2
- Status
- Consents Approved
- Technology
- Storage + Solar
- Total capacity
- 34.4 MW
- Connected now
- 0 MW
- Still to connect
- 34.4 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Embedded
- Region
- North Scotland
- Project number
- PRO-001849
- In the register since
- March 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 20 Oct 2026 registerStatus changed from Scoping to Consents Approved
- 16 Oct 2026 registerConnection date moved from 8 Oct 2029 to 31 Oct 2026 (−35 months)
- 16 Oct 2026 registerGiven a Gate 2 connection offer
- 27 Jun 2025 registerConnection date moved from 31 Oct 2025 to 8 Oct 2029 (+47 months)
- 31 Mar 2023 registerAdded to the register
Also at Lunanhead GSP
Substation viewNo other projects in the register at this connection point.