Loch na Cathrach 275kV Switching Station
North Scotland, SSEN Transmission
Read our analysis: Grid outages and the connections due by 2030
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Loch na Cathrach Pumped Storage Hydro | STATKRAFT HIGHLANDS PSH LIMITED | Hydro & marine | 550 | 28 Jun 2030 +14 mo | Gate 2 | Consents Approved |
Recent changes
- Loch na Cathrach Pumped Storage HydroNorth Scotland, Hydro & marineConnection point changed from Knocknagael 275kV to Loch na Cathrach 275kV Switching Station
- Loch na Cathrach Pumped Storage HydroNorth Scotland, Hydro & marineStage 1: Connection date moved from 30 Apr 2029 to 28 Jun 2030 (+14 months)+14 mo
- Loch na Cathrach Pumped Storage HydroNorth Scotland, Hydro & marineStage 1: Given a Gate 2 connection offerGate 2
- Loch na Cathrach Pumped Storage HydroNorth Scotland, Hydro & marineStage 2: Connection date moved from 31 Oct 2030 to 17 Nov 2031 (+13 months)+13 mo
- Loch na Cathrach Pumped Storage HydroNorth Scotland, Hydro & marineStage 2: Given a Gate 2 connection offerGate 2
- Loch na Cathrach Pumped Storage HydroNorth Scotland, Hydro & marineConnection point changed from Red John 275kV Switching Station to Knocknagael 275kV
- Loch na Cathrach Pumped Storage HydroNorth Scotland, Hydro & marineStage 1: Connection date moved from 31 Jul 2028 to 30 Apr 2029 (+9 months)+9 mo
- Loch na Cathrach Pumped Storage HydroNorth Scotland, Hydro & marineStage 2: Connection date moved from 31 Oct 2032 to 31 Oct 2030 (−24 months)−24 mo
- Loch na Cathrach Pumped Storage HydroNorth Scotland, Hydro & marineRenamed from Red John PSH
- Loch na Cathrach Pumped Storage HydroNorth Scotland, Hydro & marineStage 1: Status changed from Scoping to Consents Approved
- Loch na Cathrach Pumped Storage HydroNorth Scotland, Hydro & marineStage 2: Status changed from Scoping to Consents Approved
- Loch na Cathrach Pumped Storage HydroNorth Scotland, Hydro & marineNew stage added (100 MW from 31 Oct 2032)
- Loch na Cathrach Pumped Storage HydroNorth Scotland, Hydro & marineCustomer changed from ILI (HIGHLANDS PSH) LIMITED to STATKRAFT HIGHLANDS PSH LIMITED
- Loch na Cathrach Pumped Storage HydroNorth Scotland, Hydro & marineConnection date moved from 31 Jul 2027 to 31 Jul 2028 (+12 months)+12 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?