QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / Substation

Kirkby 275kV Substation

England and Wales, National Grid Electricity Transmission

1project in the register
400 MWstill to connect
0 MWof that with Gate 2 offers
0 MWconnected now

The queue at this substation

ProjectCustomerTechnologyQueued MWConnection dateGateStatus
Kirkby Green Energy CentreKIRKBY GREEN NG LIMITEDStorage with solar or wind40030 Oct 2028Gate 1Scoping

Recent changes

  • Kirkby Green Energy CentreEngland and Wales, Storage with solar or windMarked as Gate 1
  • Kirkby Green Energy CentreEngland and Wales, Storage with solar or windStage removed (0 MW from 30 Oct 2032)
  • Kirkby Green Energy CentreEngland and Wales, Storage with solar or windStage removed (0 MW from 30 Oct 2037)
  • Kirkby Green Energy CentreEngland and Wales, Storage with solar or windRestructured from 1 stage (400 MW from 30 Oct 2028) to 3 stages (400 MW from 30 Oct 2028, 0 MW from 30 Oct 2032, 0 MW from 30 Oct 2037)
  • Kirkby Green Energy CentreEngland and Wales, Storage with solar or windCustomer changed from KIRKBY GREEN NG LIMITED to INNOVA RENEWABLES LIMITED
  • Kirkby Green Energy CentreEngland and Wales, Storage with solar or windCustomer changed from INNOVA RENEWABLES LIMITED to KIRKBY GREEN NG LIMITED
  • Kirkby Green Energy CentreEngland and Wales, Storage with solar or windTechnology changed from Storage, Solar to Demand, Storage, Solar
  • Kirkby Green Energy CentreEngland and Wales, Storage with solar or windSubstation name updated in the register (from Kirkby 275kV to Kirkby 275kV Substation)
  • Kirkby Green Energy CentreEngland and Wales, Storage with solar or windAdded to the registerNew
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO