Kirkby Green Energy Centre
- Connection date
- 30 Oct 2028
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Demand + Storage + Solar
- Total capacity
- 400 MW
- Connected now
- 0 MW
- Still to connect
- 400 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001869
- In the register since
- May 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 16 Dec 2025 registerMarked as Gate 1
- 30 Sep 2025 registerStage removed (0 MW from 30 Oct 2032)
- 30 Sep 2025 registerStage removed (0 MW from 30 Oct 2037)
- 29 Jul 2025 registerRestructured from 1 stage (400 MW from 30 Oct 2028) to 3 stages (400 MW from 30 Oct 2028, 0 MW from 30 Oct 2032, 0 MW from 30 Oct 2037)
- 29 Apr 2025 registerCustomer changed from KIRKBY GREEN NG LIMITED to INNOVA RENEWABLES LIMITED
- 28 Mar 2025 registerCustomer changed from INNOVA RENEWABLES LIMITED to KIRKBY GREEN NG LIMITED
- 31 Jan 2025 registerTechnology changed from Storage, Solar to Demand, Storage, Solar
- 29 Jul 2022 registerSubstation name updated in the register (from Kirkby 275kV to Kirkby 275kV Substation)
- 31 May 2022 registerAdded to the register
Also at Kirkby 275kV Substation
Substation viewNo other projects in the register at this connection point.