Kilmarnock South 400kV Substation
South Scotland, SP Energy Networks
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Kilmarnock South Battery Storage | Kilmarnock Energy Centre Limited | Storage | 500 | 30 Apr 2027 | Gate 2 | Consents Approved |
| Zenobe Kilmarnock South | ZENOBE KILMARNOCK SOUTH LIMITED | Storage | 0 | Connected | Not stated | Built |
Recent changes
- Kilmarnock South Battery StorageSouth Scotland, StorageStatus changed from Scoping to Consents Approved
- Zenobe Kilmarnock SouthSouth Scotland, Storage300 MW now connectedConnected
- Zenobe Kilmarnock SouthSouth Scotland, StorageStatus changed from Scoping to Built
- Kilmarnock South Battery StorageSouth Scotland, StorageGiven a Gate 2 connection offerGate 2
- Zenobe Kilmarnock SouthSouth Scotland, StorageRenamed from Zenobe Energy Kilmarnock South
- Kilmarnock South Battery StorageSouth Scotland, StorageConnection point changed from Kilmarnock South 275/33kV to Kilmarnock South 400kV Substation
- Kilmarnock South Battery StorageSouth Scotland, StorageCustomer changed from WEAVER POWER LIMITED to Kilmarnock Energy Centre Limited
- Zenobe Kilmarnock SouthSouth Scotland, StorageConnection point changed from Kilmarnock South 275/33kV to Kilmarnock South 400kV Substation
- Kilmarnock South Battery StorageSouth Scotland, StorageConnection point changed from Kilmarnock South 400/275/33kV to Kilmarnock South 275/33kV
- Zenobe Kilmarnock SouthSouth Scotland, StorageConnection point changed from Kilmarnock South 400/275/33kV to Kilmarnock South 275/33kV
- Kilmarnock South Battery StorageSouth Scotland, StorageSubstation name updated in the register (from Kilmarnock South GSP to Kilmarnock South 400/275/33kV)
- Zenobe Kilmarnock SouthSouth Scotland, StorageSubstation name updated in the register (from Kilmarnock South GSP to Kilmarnock South 400/275/33kV)
- Zenobe Kilmarnock SouthSouth Scotland, StorageRenamed from Zenobe Kilmarnock South
- Zenobe Kilmarnock SouthSouth Scotland, StorageRestructured from 2 stages (200 MW from 25 Oct 2024, 100 MW from 31 Jul 2025) to 1 stage (300 MW from 29 Aug 2025). First connection date +10 months+10 mo
- Zenobe Kilmarnock SouthSouth Scotland, StorageRestructured from 1 stage (300 MW from 25 Oct 2024) to 2 stages (200 MW from 25 Oct 2024, 100 MW from 31 Jul 2025)
- Zenobe Kilmarnock SouthSouth Scotland, StorageCustomer changed from ZENOBE ENERGY LIMITED to Zenobē Kilmarnock South Limited
- Zenobe Kilmarnock SouthSouth Scotland, StorageCapacity changed from 200 MW to 300 MW
- Kilmarnock South Battery StorageSouth Scotland, StorageSubstation name updated in the register (from Kilmarnock South to Kilmarnock South GSP)
- Zenobe Kilmarnock SouthSouth Scotland, StorageSubstation name updated in the register (from Kilmarnock South to Kilmarnock South GSP)
- Kilmarnock South Battery StorageSouth Scotland, StorageCapacity changed from 300 MW to 500 MW
- Kilmarnock South Battery StorageSouth Scotland, StorageAdded to the registerNew
- Zenobe Kilmarnock SouthSouth Scotland, StorageAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?