Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / South Scotland

Zenobe Kilmarnock South

ZENOBE KILMARNOCK SOUTH LIMITED at Kilmarnock South 400kV Substation

Connection date
Connected
Gate
Not stated
Status
Built
Planning consent
Operational since 21 Jan 2026
Scottish Government (S36), reference ECU00003435 · Source: REPD
Technology
Storage
Total capacity
300 MW
Connected now
300 MW
Still to connect
0 MW
Transmission owner
SP Energy Networks (SPT)
Agreement type
Direct Connection
Region
South Scotland
Project number
PRO-001687
In the register since
November 2021

What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 12 Jun 2026 register
    300 MW now connected
  • 12 Jun 2026 register
    Status changed from Scoping to Built
  • 21 Nov 2025 register
    Renamed from Zenobe Energy Kilmarnock South
  • 24 Dec 2024 register
    Connection point changed from Kilmarnock South 275/33kV to Kilmarnock South 400kV Substation
  • 29 Oct 2024 register
    Connection point changed from Kilmarnock South 400/275/33kV to Kilmarnock South 275/33kV
  • 27 Sep 2024 register
    Substation name updated in the register (from Kilmarnock South GSP to Kilmarnock South 400/275/33kV)
  • 31 May 2024 register
    Renamed from Zenobe Kilmarnock South
  • 26 Apr 2024 register
    Restructured from 2 stages (200 MW from 25 Oct 2024, 100 MW from 31 Jul 2025) to 1 stage (300 MW from 29 Aug 2025). First connection date +10 months
  • 31 Mar 2023 register
    Restructured from 1 stage (300 MW from 25 Oct 2024) to 2 stages (200 MW from 25 Oct 2024, 100 MW from 31 Jul 2025)
  • 28 Feb 2023 register
    Customer changed from ZENOBE ENERGY LIMITED to Zenobē Kilmarnock South Limited
  • 28 Feb 2023 register
    Capacity changed from 200 MW to 300 MW
  • 23 Dec 2022 register
    Substation name updated in the register (from Kilmarnock South to Kilmarnock South GSP)
  • 30 Nov 2021 register
    Added to the register

Also at Kilmarnock South 400kV Substation

Substation view

1 other project, 500 MW still to connect at this substation in total.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO