Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / Substation

Killingholme 400kV Substation

England and Wales, National Grid Electricity Transmission

3projects in the register
1 GWstill to connect
0 MWof that with Gate 2 offers
619 MWconnected now

The queue at this substation

ProjectCustomerTechnologyQueued MWConnection dateGateStatus
North Killingholme Power ProjectUniper UK LimitedThermal (gas, biomass, waste)54030 Sep 2030Not statedConsents Approved
THE CLEAN FUTURETHE CLEAN FUTURE RENEWABLES LIMITEDStorage with solar or wind50031 May 2033Not statedScoping
KillingholmeUniper UK LimitedThermal (gas, biomass, waste)0ConnectedNot statedBuilt

Recent changes

  • KillingholmeEngland and Wales, Thermal (gas, biomass, waste)Customer changed from C.GEN Killingholme Limited to Uniper UK Limited
  • North Killingholme Power ProjectEngland and Wales, Thermal (gas, biomass, waste)Customer changed from C.GEN Killingholme Limited to Uniper UK Limited
  • KillingholmeEngland and Wales, Thermal (gas, biomass, waste)Customer changed from Uniper UK Limited to C.GEN Killingholme Limited
  • North Killingholme Power ProjectEngland and Wales, Thermal (gas, biomass, waste)Customer changed from Uniper UK Limited to C.GEN Killingholme Limited
  • North Killingholme Power ProjectEngland and Wales, Thermal (gas, biomass, waste)Customer changed from C.GEN KILLINGHOLME LIMITED to UNIPER UK LIMITED
  • North Killingholme Power ProjectEngland and Wales, Thermal (gas, biomass, waste)Connection date moved from 31 Oct 2026 to 30 Sep 2030 (+47 months)+47 mo
  • KillingholmeEngland and Wales, Thermal (gas, biomass, waste)Restructured from 2 stages (19 MW from 1 Apr 2024, 600 MW connected) to 1 stage (619 MW connected)
  • North Killingholme Power ProjectEngland and Wales, Thermal (gas, biomass, waste)Connection date moved from 1 Apr 2023 to 31 Oct 2026 (+43 months)+43 mo
  • KillingholmeEngland and Wales, Thermal (gas, biomass, waste)Substation name updated in the register (from Killingholme 400kV to Killingholme 400kV Substation)
  • North Killingholme Power ProjectEngland and Wales, Thermal (gas, biomass, waste)Substation name updated in the register (from Killingholme 400kV to Killingholme 400kV Substation)
  • THE CLEAN FUTUREEngland and Wales, Storage with solar or windSubstation name updated in the register (from Killingholme 400kV to Killingholme 400kV Substation)
  • THE CLEAN FUTUREEngland and Wales, Storage with solar or windAdded to the registerNew
  • KillingholmeEngland and Wales, Thermal (gas, biomass, waste)New stage added (19 MW from 1 Apr 2024)
  • North Killingholme Power ProjectEngland and Wales, Thermal (gas, biomass, waste)Connection date moved from 4 Jan 2023 to 1 Apr 2023 (+3 months)+3 mo
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO