North Killingholme Power Project
- Connection date
- 30 Sep 2030
- Gate
- Not stated
- Status
- Consents Approved
- Planning consent
- Granted 11 Sep 2014
North Killingholme Power Project (EN010038) · Source: Planning Inspectorate - Technology
- Gas (CCGT)
- Total capacity
- 540 MW
- Connected now
- 0 MW
- Still to connect
- 540 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001038
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 27 Jan 2026 registerCustomer changed from C.GEN Killingholme Limited to Uniper UK Limited
- 16 Dec 2025 registerCustomer changed from Uniper UK Limited to C.GEN Killingholme Limited
- 28 Mar 2025 registerCustomer changed from C.GEN KILLINGHOLME LIMITED to UNIPER UK LIMITED
- 24 Dec 2024 registerConnection date moved from 31 Oct 2026 to 30 Sep 2030 (+47 months)
- 28 Apr 2023 registerConnection date moved from 1 Apr 2023 to 31 Oct 2026 (+43 months)
- 23 Dec 2022 registerSubstation name updated in the register (from Killingholme 400kV to Killingholme 400kV Substation)
- 26 Feb 2021 registerConnection date moved from 4 Jan 2023 to 1 Apr 2023 (+3 months)
Also at Killingholme 400kV Substation
Substation view2 other projects, 1 GW still to connect at this substation in total.