Hurlie 400kV substation
North Scotland, SSEN Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Bellrock Offshore Wind Farm | Bellrock Offshore Wind Farm Limited | Offshore wind | 1,800 | 31 Oct 2032 | Not stated | Scoping |
| Cerulean Winds INTOG 1 | CERULEAN WINDS LIMITED | Offshore wind | 600 | 31 Oct 2033 | Not stated | Awaiting Consents |
| Bowdun (ex Cluaran Deas Ear) Offshore Wind Farm | BOWDUN OFFSHORE WIND FARM LIMITED | Offshore wind | 1,008 | 31 Dec 2035 | Not stated | Awaiting Consents |
Recent changes
- Bowdun (ex Cluaran Deas Ear) Offshore Wind FarmNorth Scotland, Offshore windStatus changed from Scoping to Awaiting Consents
- Cerulean Winds INTOG 1North Scotland, Offshore windConnection point changed from Peterhead 400kV Substation to Hurlie 400kV substation
- Bellrock Offshore Wind FarmNorth Scotland, Offshore windCustomer changed from BLUEFLOAT ENERGY UK HOLDINGS LIMITED to Bellrock Offshore Wind Farm Limited
- Bellrock Offshore Wind FarmNorth Scotland, Offshore windConnection point changed from Lyra 320/66kV Offshore Substation to Hurlie 400kV substation
- Bowdun (ex Cluaran Deas Ear) Offshore Wind FarmNorth Scotland, Offshore windConnection point changed from New Deer 2 400kV Substation to Hurlie 400kV substation
- Bellrock Offshore Wind FarmNorth Scotland, Offshore windRestructured from 1 stage (1,200 MW from 31 Oct 2033) to 2 stages (1,200 MW from 31 Oct 2032, 600 MW from 31 Oct 2035). First connection date −12 months−12 mo
- Bellrock Offshore Wind FarmNorth Scotland, Offshore windTransmission owner changed from SPT to SHET
- Bowdun (ex Cluaran Deas Ear) Offshore Wind FarmNorth Scotland, Offshore windConnection date moved from 31 Oct 2033 to 31 Dec 2035 (+26 months)+26 mo
- Cerulean Winds INTOG 1North Scotland, Offshore windAdded to the registerNew
- Bellrock Offshore Wind FarmNorth Scotland, Offshore windRenamed from Lyra Offshore Wind Farm
- Bowdun (ex Cluaran Deas Ear) Offshore Wind FarmNorth Scotland, Offshore windCustomer changed from THISTLE WIND PARTNERS CLUARAN DEAS EAR Limited to BOWDUN OFFSHORE WIND FARM LIMITED
- Bowdun (ex Cluaran Deas Ear) Offshore Wind FarmNorth Scotland, Offshore windRenamed from Cluaran Deas Ear Offshore Wind Farm
- Bowdun (ex Cluaran Deas Ear) Offshore Wind FarmNorth Scotland, Offshore windAdded to the registerNew
- Bellrock Offshore Wind FarmNorth Scotland, Offshore windAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?