Cerulean Winds INTOG 1
- Connection date
- 31 Oct 2033
- Gate
- Not stated
- Status
- Awaiting Consents
- Technology
- Demand + Offshore wind
- Total capacity
- 600 MW
- Connected now
- 0 MW
- Still to connect
- 600 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-004330
- In the register since
- December 2024
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 30 Jan 2026 registerConnection point changed from Peterhead 400kV Substation to Hurlie 400kV substation
- 24 Dec 2024 registerAdded to the register
Also at Hurlie 400kV substation
Substation view2 other projects, 3.4 GW still to connect at this substation in total. 1.2 GW is due to connect here before this project’s connection date of 31 Oct 2033.