Glenmuckloch 132kV Substation
South Scotland, SP Energy Networks
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Glenmuckloch Pumped Storage | GLENMUCKLOCH PUMPED STORAGE HYDRO LIMITED | Hydro & marine | 210 | 18 May 2029 | Not stated | Consents Approved |
| Lagrae Battery Storage | LAGRAE BATTERY STORAGE LIMITED | Storage | 400 | 31 Oct 2036 | Gate 1 | Scoping |
| The Drum Wind Farm | WIND ESTATE (UK) LIMITED | Onshore wind | 57.6 | 31 Oct 2037 | Gate 1 | Scoping |
Recent changes
- The Drum Wind FarmSouth Scotland, Onshore windMarked as Gate 1
- The Drum Wind FarmSouth Scotland, Onshore windConnection point changed from The Drum 132KV Substation to Glenmuckloch 132kV Substation
- Lagrae Battery StorageSouth Scotland, StorageMarked as Gate 1
- The Drum Wind FarmSouth Scotland, Onshore windAdded to the registerNew
- Glenmuckloch Pumped StorageSouth Scotland, Hydro & marineConnection point changed from Glenmuckloch 132/33kV to Glenmuckloch 132kV Substation
- Glenmuckloch Pumped StorageSouth Scotland, Hydro & marineConnection date moved from 1 Oct 2028 to 18 May 2029 (+8 months)+8 mo
- Glenmuckloch Pumped StorageSouth Scotland, Hydro & marineConnection date moved from 30 Jun 2027 to 1 Oct 2028 (+15 months)+15 mo
- Lagrae Battery StorageSouth Scotland, StorageAdded to the registerNew
- Glenmuckloch Pumped StorageSouth Scotland, Hydro & marineSubstation name updated in the register (from Glenmuckloch 132kV/33kV Substation to Glenmuckloch 132/33kV)
- Glenmuckloch Pumped StorageSouth Scotland, Hydro & marineConnection point changed from Glenmuckloch 132kV Substation to Glenmuckloch 132kV/33kV Substation
- Glenmuckloch Pumped StorageSouth Scotland, Hydro & marineConnection date moved from 31 Oct 2026 to 30 Jun 2027 (+8 months)+8 mo
- Glenmuckloch Pumped StorageSouth Scotland, Hydro & marineConnection date moved from 30 May 2025 to 31 Oct 2026 (+17 months)+17 mo
- Glenmuckloch Pumped StorageSouth Scotland, Hydro & marineConnection date moved from 30 Apr 2024 to 30 May 2025 (+13 months)+13 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?