The Drum Wind Farm
- Connection date
- 31 Oct 2037
- Gate
- Gate 1
- Status
- Scoping
- Planning consent
- Refused 1 Oct 2025
East Ayrshire, reference 22/0792/PP · Source: REPD - Technology
- Onshore wind
- Total capacity
- 57.6 MW
- Connected now
- 0 MW
- Still to connect
- 57.6 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-006069
- In the register since
- June 2025
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 1 May 2026 registerMarked as Gate 1
- 7 Apr 2026 registerConnection point changed from The Drum 132KV Substation to Glenmuckloch 132kV Substation
- 27 Jun 2025 registerAdded to the register
Also at Glenmuckloch 132kV Substation
Substation view2 other projects, 668 MW still to connect at this substation in total. 610 MW is due to connect here before this project’s connection date of 31 Oct 2037.