Gills Bay GSP
North Scotland, SSEN Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| MeyGen Tidal | Meygrid Limited | Hydro & marine | 287 | 1 Apr 2027 | Not stated | Consents Approved |
Recent changes
- MeyGen TidalNorth Scotland, Hydro & marineStage 2: Capacity changed from 43 MW to 209 MW
- MeyGen TidalNorth Scotland, Hydro & marineStage 3: Capacity changed from 83 MW to 50 MW
- MeyGen TidalNorth Scotland, Hydro & marineStage 3: Connection date moved from 1 Apr 2028 to 31 Oct 2030 (+31 months)+31 mo
- MeyGen TidalNorth Scotland, Hydro & marineStage 3: Status changed from Awaiting Consents to Scoping
- MeyGen TidalNorth Scotland, Hydro & marineStage removed (83 MW from 1 Apr 2028)
- MeyGen TidalNorth Scotland, Hydro & marineStage removed (50 MW from 31 Oct 2030)
- MeyGen TidalNorth Scotland, Hydro & marineCustomer changed from MEYGEN PLC to Meygrid Limited
- MeyGen TidalNorth Scotland, Hydro & marineStage 1: Technology changed from Tidal to Storage, Tidal
- MeyGen TidalNorth Scotland, Hydro & marineStage 2: Technology changed from Tidal to Storage, Tidal
- MeyGen TidalNorth Scotland, Hydro & marineStage 3: Technology changed from Tidal to Storage, Tidal
- MeyGen TidalNorth Scotland, Hydro & marineStage 4: Technology changed from Tidal to Storage, Tidal
- MeyGen TidalNorth Scotland, Hydro & marineStage 5: Technology changed from Tidal to Storage, Tidal
- MeyGen TidalNorth Scotland, Hydro & marineStage 1: Capacity changed from 15 MW to 28 MW
- MeyGen TidalNorth Scotland, Hydro & marineStage 2: Capacity changed from 56 MW to 43 MW
- MeyGen TidalNorth Scotland, Hydro & marineStage 2: Connection date moved from 1 Apr 2027 to 1 Apr 2028 (+12 months)+12 mo
- MeyGen TidalNorth Scotland, Hydro & marineStage 3: Connection date moved from 1 Apr 2027 to 1 Apr 2028 (+12 months)+12 mo
- MeyGen TidalNorth Scotland, Hydro & marineStage 4: Connection date moved from 1 Apr 2027 to 1 Apr 2028 (+12 months)+12 mo
- MeyGen TidalNorth Scotland, Hydro & marineNew stage added (50 MW from 31 Oct 2030)
- MeyGen TidalNorth Scotland, Hydro & marineStage 1: Connection date moved from 31 Mar 2026 to 1 Apr 2027 (+12 months)+12 mo
- MeyGen TidalNorth Scotland, Hydro & marineStage 2: Connection date moved from 31 Mar 2026 to 1 Apr 2027 (+12 months)+12 mo
- MeyGen TidalNorth Scotland, Hydro & marineStage 3: Connection date moved from 1 Apr 2026 to 1 Apr 2027 (+12 months)+12 mo
- MeyGen TidalNorth Scotland, Hydro & marineStage 1: Connection date moved from 1 Apr 2025 to 31 Mar 2026 (+12 months)+12 mo
- MeyGen TidalNorth Scotland, Hydro & marineStage 2: Connection date moved from 1 Apr 2025 to 31 Mar 2026 (+12 months)+12 mo
- MeyGen TidalNorth Scotland, Hydro & marineSubstation name updated in the register (from Gills Bay to Gills Bay GSP)
- MeyGen TidalNorth Scotland, Hydro & marineStage 1: Connection date moved from 31 Oct 2024 to 1 Apr 2025 (+5 months)+5 mo
- MeyGen TidalNorth Scotland, Hydro & marineStage 2: Connection date moved from 31 Oct 2024 to 1 Apr 2025 (+5 months)+5 mo
- MeyGen TidalNorth Scotland, Hydro & marineStage 3: Connection date moved from 31 Oct 2025 to 1 Apr 2026 (+5 months)+5 mo
- MeyGen TidalNorth Scotland, Hydro & marineStage 4: Connection date moved from 31 Oct 2026 to 1 Apr 2027 (+5 months)+5 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?