Fiddlers Ferry 275kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| SSE Fiddlers Ferry Battery Energy Storage | LITTLETON PASTURES SOLAR LIMITED | Storage | 150 | 12 Feb 2027 +3 mo | Gate 2 | Consents Approved |
| Penketh Hall Farm | Net Zero One Ltd | Storage | 250 | 1 Sep 2027 | Gate 1 | Scoping |
| Fiddlers Ferry BESS | FIDDLERS FERRY LTD | Storage | 900 | 31 Oct 2027 | Gate 2 | Consents Approved |
Recent changes
- Fiddlers Ferry BESSEngland and Wales, StorageStage 2: Given a Gate 2 connection offerGate 2
- Fiddlers Ferry BESSEngland and Wales, StorageStage 3: Given a Gate 2 connection offerGate 2
- SSE Fiddlers Ferry Battery Energy StorageEngland and Wales, StorageCustomer changed from SSE FIDDLERS FERRY BATTERY LIMITED to LITTLETON PASTURES SOLAR LIMITED
- SSE Fiddlers Ferry Battery Energy StorageEngland and Wales, StorageStatus changed from Scoping to Consents Approved
- SSE Fiddlers Ferry Battery Energy StorageEngland and Wales, StorageGiven a Gate 2 connection offerGate 2
- Fiddlers Ferry BESSEngland and Wales, StorageStage 1: Status changed from Scoping to Consents Approved
- Fiddlers Ferry BESSEngland and Wales, StorageStage 2: Status changed from Scoping to Consents Approved
- Fiddlers Ferry BESSEngland and Wales, StorageStage 3: Status changed from Scoping to Consents Approved
- Fiddlers Ferry BESSEngland and Wales, StorageStage 1: Technology changed from Demand, Storage to Storage
- Fiddlers Ferry BESSEngland and Wales, StorageStage 1: Given a Gate 2 connection offerGate 2
- SSE Fiddlers Ferry Battery Energy StorageEngland and Wales, StorageConnection date moved from 30 Oct 2026 to 12 Feb 2027 (+3 months)+3 mo
- Penketh Hall FarmEngland and Wales, StorageMarked as Gate 1
- SSE Fiddlers Ferry Battery Energy StorageEngland and Wales, StorageConnection date moved from 12 Feb 2027 to 30 Oct 2026 (−3 months)−3 mo
- SSE Fiddlers Ferry Battery Energy StorageEngland and Wales, StorageGate marking removed (was Gate 2)
- SSE Fiddlers Ferry Battery Energy StorageEngland and Wales, StorageConnection date moved from 30 Oct 2026 to 12 Feb 2027 (+3 months)+3 mo
- SSE Fiddlers Ferry Battery Energy StorageEngland and Wales, StorageGiven a Gate 2 connection offerGate 2
- SSE Fiddlers Ferry Battery Energy StorageEngland and Wales, StorageStage removed (0 MW from 1 Nov 2037)
- SSE Fiddlers Ferry Battery Energy StorageEngland and Wales, StorageCustomer changed from SSE UTILITY SOLUTIONS LIMITED to SSE FIDDLERS FERRY BATTERY LIMITED
- SSE Fiddlers Ferry Battery Energy StorageEngland and Wales, StorageStage 2: Capacity changed from 150 MW to 0 MW
- SSE Fiddlers Ferry Battery Energy StorageEngland and Wales, StorageStage removed (150 MW from 30 Apr 2025)
- Fiddlers Ferry BESSEngland and Wales, StorageRestructured from 1 stage (900 MW from 30 Nov 2037) to 3 stages (300 MW from 31 Oct 2027, 300 MW from 31 Oct 2028, 300 MW from 31 Oct 2029). First connection date −121 months−121 mo
- SSE Fiddlers Ferry Battery Energy StorageEngland and Wales, StorageNew stage added (150 MW from 30 Oct 2026)
- SSE Fiddlers Ferry Battery Energy StorageEngland and Wales, StorageNew stage added (150 MW from 1 Nov 2037)
- SSE Fiddlers Ferry Battery Energy StorageEngland and Wales, StorageCustomer changed from SSE FIDDLERS FERRY BATTERY LIMITED to SSE UTILITY SOLUTIONS LIMITED
- SSE Fiddlers Ferry Battery Energy StorageEngland and Wales, StorageCustomer changed from SSE UTILITY SOLUTIONS LIMITED to SSE FIDDLERS FERRY BATTERY LIMITED
- SSE Fiddlers Ferry Battery Energy StorageEngland and Wales, StorageConnection date moved from 30 Jun 2024 to 30 Apr 2025 (+10 months)+10 mo
- Fiddlers Ferry BESSEngland and Wales, StorageAdded to the registerNew
- SSE Fiddlers Ferry Battery Energy StorageEngland and Wales, StorageStatus changed from Scoping to Awaiting Consents
- Penketh Hall FarmEngland and Wales, StorageSubstation name updated in the register (from Fiddlers Ferry 275kV to Fiddlers Ferry 275kV Substation)
- SSE Fiddlers Ferry Battery Energy StorageEngland and Wales, StorageSubstation name updated in the register (from Fiddlers Ferry 275kV to Fiddlers Ferry 275kV Substation)
- Penketh Hall FarmEngland and Wales, StorageAdded to the registerNew
- SSE Fiddlers Ferry Battery Energy StorageEngland and Wales, StorageAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose