Fiddlers Ferry BESS
- Connection date
- 31 Oct 2027
- Gate
- Gate 2
- Status
- Consents Approved
- Technology
- Demand + Storage
- Total capacity
- 900 MW
- Connected now
- 0 MW
- Still to connect
- 900 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-003897
- In the register since
- June 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 0 | 300 | 300 | 31 Oct 2027 | Gate 2 | Consents Approved |
| 2 | 0 | 300 | 600 | 31 Oct 2028 | Gate 2 | Consents Approved |
| 3 | 0 | 300 | 900 | 31 Oct 2029 | Gate 2 | Consents Approved |
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 22 Oct 2026 registerStage 2: Given a Gate 2 connection offer
- 22 Oct 2026 registerStage 3: Given a Gate 2 connection offer
- 18 Sep 2026 registerStage 1: Status changed from Scoping to Consents Approved
- 18 Sep 2026 registerStage 2: Status changed from Scoping to Consents Approved
- 18 Sep 2026 registerStage 3: Status changed from Scoping to Consents Approved
- 14 Aug 2026 registerStage 1: Technology changed from Demand, Storage to Storage
- 14 Aug 2026 registerStage 1: Given a Gate 2 connection offer
- 27 Jun 2025 registerRestructured from 1 stage (900 MW from 30 Nov 2037) to 3 stages (300 MW from 31 Oct 2027, 300 MW from 31 Oct 2028, 300 MW from 31 Oct 2029). First connection date −121 months
- 30 Jun 2023 registerAdded to the register
Also at Fiddlers Ferry 275kV Substation
Substation view2 other projects, 1.3 GW still to connect at this substation in total. 400 MW is due to connect here before this project’s connection date of 31 Oct 2027.