Elderslie 132/33kV
South Scotland, SP Energy Networks
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Middleton Farm Solar | Bluestone Middleton Farm 1 Ltd | Solar | 38.7 | 28 Jun 2028 +33 mo | Not stated | Scoping |
| Well Street Paisley | Gas Generation Property Limited | Storage | 49.9 | 28 Jun 2028 +38 mo | Gate 2 | Consents Approved |
Recent changes
- Middleton Farm SolarSouth Scotland, SolarCustomer changed from Bluestone Energy Ltd to Bluestone Middleton Farm 1 Ltd
- Well Street PaisleySouth Scotland, StorageStatus changed from Scoping to Consents Approved
- Middleton Farm SolarSouth Scotland, SolarConnection date moved from 6 Oct 2025 to 28 Jun 2028 (+33 months)+33 mo
- Middleton Farm SolarSouth Scotland, SolarCustomer changed from Bluestone Middleton Farm 1 Ltd to Bluestone Energy Ltd
- Well Street PaisleySouth Scotland, StorageConnection date moved from 6 May 2025 to 28 Jun 2028 (+38 months)+38 mo
- Well Street PaisleySouth Scotland, StorageGiven a Gate 2 connection offerGate 2
- Middleton Farm SolarSouth Scotland, SolarCustomer changed from Bluestone Energy Ltd to Bluestone Middleton Farm 1 Ltd
- Middleton Farm SolarSouth Scotland, SolarSubstation name updated in the register (from Elderslie 132/33kV Substation to Elderslie 132/33kV)
- Well Street PaisleySouth Scotland, StorageSubstation name updated in the register (from Elderslie 132/33kV Substation to Elderslie 132/33kV)
- Well Street PaisleySouth Scotland, StorageCustomer changed from Lark Gas Assets Limited to Gas Generation Property Limited
- Well Street PaisleySouth Scotland, StorageAdded to the registerNew
- Middleton Farm SolarSouth Scotland, SolarAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?