Well Street Paisley
- Connection date
- 28 Jun 2028 +38 months since 9 Dec
- Gate
- Gate 2
- Status
- Consents Approved
- Planning consent
- Granted 23 May 2023
Renfrewshire, reference 23/0018/PP · Source: REPD - Technology
- Storage
- Total capacity
- 49.9 MW
- Connected now
- 0 MW
- Still to connect
- 49.9 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Embedded
- Region
- South Scotland
- Project number
- PRO-002265
- In the register since
- August 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 18 Sep 2026 registerStatus changed from Scoping to Consents Approved
- 19 Jun 2026 registerConnection date moved from 6 May 2025 to 28 Jun 2028 (+38 months)
- 19 Jun 2026 registerGiven a Gate 2 connection offer
- 27 Sep 2024 registerSubstation name updated in the register (from Elderslie 132/33kV Substation to Elderslie 132/33kV)
- 28 Nov 2023 registerCustomer changed from Lark Gas Assets Limited to Gas Generation Property Limited
- 29 Aug 2023 registerAdded to the register
Also at Elderslie 132/33kV
Substation view1 other project, 88.6 MW still to connect at this substation in total.