Eggborough 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Eggborough CCGT - OCGT - BESS | EGGBOROUGH POWER LIMITED | Thermal (gas, biomass, waste) | 2,450 | 1 Oct 2026 Past date | Not stated | Awaiting Consents |
| Eggborough | SSE EGGBOROUGH LIMITED | Storage | 550 | 16 Jun 2032 | Not stated | Scoping |
Left the register since January 2021: Eggborough (Coal) (0 MW).
Recent changes
- EggboroughEngland and Wales, StorageTechnology changed from Storage, Solar to Storage
- Eggborough CCGT - OCGT - BESSEngland and Wales, Thermal (gas, biomass, waste)Renamed from Eggborough CCGT OCGT and BESS
- Eggborough CCGT - OCGT - BESSEngland and Wales, Thermal (gas, biomass, waste)Renamed from Eggborough CCGT and BESS
- Eggborough CCGT - OCGT - BESSEngland and Wales, Thermal (gas, biomass, waste)Restructured from 1 stage (2,450 MW from 1 Oct 2026) to 2 stages (1,999 MW from 1 Oct 2026, 451 MW from 1 Oct 2027)
- EggboroughEngland and Wales, StorageCustomer changed from SSE UTILITY SOLUTIONS LIMITED to SSE EGGBOROUGH LIMITED
- Eggborough CCGT - OCGT - BESSEngland and Wales, Thermal (gas, biomass, waste)Renamed from Eggborough
- Eggborough (Coal)England and Wales, Thermal (gas, biomass, waste)Left the register (0 MW)0 MW
- EggboroughEngland and Wales, StorageRenamed from Eggborough GSP
- EggboroughEngland and Wales, StorageSubstation name updated in the register (from Eggborough 400kV to Eggborough 400kV Substation)
- Eggborough CCGT - OCGT - BESSEngland and Wales, Thermal (gas, biomass, waste)Substation name updated in the register (from Eggborough 400kV to Eggborough 400kV Substation)
- Eggborough (Coal)England and Wales, Thermal (gas, biomass, waste)Substation name updated in the register (from Eggborough 400kV to Eggborough 400kV Substation)
- Eggborough CCGT - OCGT - BESSEngland and Wales, Thermal (gas, biomass, waste)Connection date moved from 1 Oct 2025 to 1 Oct 2026 (+12 months)+12 mo
- EggboroughEngland and Wales, StorageAdded to the registerNew
- Eggborough CCGT - OCGT - BESSEngland and Wales, Thermal (gas, biomass, waste)Connection date moved from 1 Oct 2024 to 1 Oct 2025 (+12 months)+12 mo
- Eggborough CCGT - OCGT - BESSEngland and Wales, Thermal (gas, biomass, waste)Connection date moved from 10 Jan 2024 to 1 Oct 2024 (+9 months)+9 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose