Earba PSH Powerhouse Substation
North Scotland, SSEN Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Earba PSH | EARBA LIMITED | Hydro & marine | 1,800 | 31 Dec 2032 | Not stated | Consents Approved |
Left the register since January 2021: Earba PSH (900 MW).
Recent changes
- Earba PSHNorth Scotland, Hydro & marineStage 1: Connection date moved from 31 Oct 2029 to 31 Dec 2032 (+38 months)+38 mo
- Earba PSHNorth Scotland, Hydro & marineStage 1: Status changed from Scoping to Consents Approved
- Earba PSHNorth Scotland, Hydro & marineStage 2: Capacity changed from 900 MW to 1,200 MW
- Earba PSHNorth Scotland, Hydro & marineStage 2: Status changed from Scoping to Consents Approved
- Earba PSHNorth Scotland, Hydro & marineCustomer changed from GILKES ENERGY LIMITED to EARBA LIMITED
- Earba PSHNorth Scotland, Hydro & marineCustomer changed from EARBA LIMITED to GILKES ENERGY LIMITED
- Earba PSHNorth Scotland, Hydro & marineCustomer changed from GILKES ENERGY LIMITED to EARBA LIMITED
- Earba PSHNorth Scotland, Hydro & marineRenamed from Dunstable
- Earba PSHNorth Scotland, Hydro & marineCustomer changed from Connectid 9 Limited to GILKES ENERGY LIMITED
- Earba PSHNorth Scotland, Hydro & marineAdded to the registerNew
- Earba PSHNorth Scotland, Hydro & marineLeft the register (900 MW from 31 Oct 2029)900 MW
- Earba PSHNorth Scotland, Hydro & marineCapacity changed from 600 MW to 900 MW
- Earba PSHNorth Scotland, Hydro & marineAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?