Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / Substation

Dunstable 400kV Substation

England and Wales, National Grid Electricity Transmission

5projects in the register
2.8 GWstill to connect
0 MWof that with Gate 2 offers
0 MWconnected now

The queue at this substation

ProjectCustomerTechnologyQueued MWConnection dateGateStatus
Woburn Solar FarmSolarThree LtdSolar84031 Oct 2031Gate 1Scoping
Hipsey BESSKONA ASSET 2 LIMITEDStorage24029 Oct 2032Gate 1Scoping
Hockliffe GEC (Ethos Green)HOCKLIFFE GREEN ENERGY CENTRE LTDStorage with solar or wind85029 Oct 2032Gate 1Scoping
Sundon Farm548 UK INVESTMENT HOLDINGS LIMITEDStorage with solar or wind20029 Oct 2032Gate 1Scoping
Sundon Farm 2548 UK INVESTMENT HOLDINGS LIMITEDStorage with solar or wind70029 Oct 2032Gate 1Scoping

Recent changes

  • Hockliffe GEC (Ethos Green)England and Wales, Storage with solar or windMarked as Gate 1
  • Sundon FarmEngland and Wales, Storage with solar or windAdded to the registerNew
  • Sundon Farm 2England and Wales, Storage with solar or windAdded to the registerNew
  • Hockliffe GEC (Ethos Green)England and Wales, Storage with solar or windTechnology changed from Demand, Storage, Solar, Reactive compensation to Storage, Solar
  • Sundon FarmEngland and Wales, Storage with solar or windLeft the register (200 MW from 29 Oct 2032)200 MW
  • Sundon Farm 2England and Wales, Storage with solar or windLeft the register (700 MW from 29 Oct 2032)700 MW
  • Woburn Solar FarmEngland and Wales, SolarMarked as Gate 1
  • Sundon Farm 2England and Wales, Storage with solar or windMarked as Gate 1
  • Hipsey BESSEngland and Wales, StorageMarked as Gate 1
  • Sundon FarmEngland and Wales, Storage with solar or windMarked as Gate 1
  • Sundon FarmEngland and Wales, Storage with solar or windConnection point changed from Sundon 400kV Substation to Dunstable 400kV Substation
  • Sundon FarmEngland and Wales, Storage with solar or windConnection date moved from 30 Apr 2033 to 29 Oct 2032 (−6 months)−6 mo
  • Sundon Farm 2England and Wales, Storage with solar or windConnection point changed from Sundon 400kV Substation to Dunstable 400kV Substation
  • Hipsey BESSEngland and Wales, StorageConnection point changed from Sundon 400kV Substation to Dunstable 400kV Substation
  • Hockliffe GEC (Ethos Green)England and Wales, Storage with solar or windAdded to the registerNew
  • Hipsey BESSEngland and Wales, StorageAdded to the registerNew
  • Sundon FarmEngland and Wales, Storage with solar or windAdded to the registerNew
  • Sundon Farm 2England and Wales, Storage with solar or windAdded to the registerNew
  • Woburn Solar FarmEngland and Wales, SolarAdded to the registerNew
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO