Hipsey BESS
- Connection date
- 29 Oct 2032
- Gate
- Gate 1
- Status
- Scoping
- Planning consent
- Granted 6 Jan 2025
Central Bedfordshire, reference CB/24/00414/FULL · Source: REPD - Technology
- Storage
- Total capacity
- 240 MW
- Connected now
- 0 MW
- Still to connect
- 240 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-003051
- In the register since
- July 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 28 Nov 2025 registerMarked as Gate 1
- 27 Feb 2024 registerConnection point changed from Sundon 400kV Substation to Dunstable 400kV Substation
- 28 Jul 2023 registerAdded to the register
Also at Dunstable 400kV Substation
Substation view4 other projects, 2.8 GW still to connect at this substation in total. 840 MW is due to connect here before this project’s connection date of 29 Oct 2032.
- Woburn Solar FarmSolarThree Ltd, Solar, Gate 1Oct 2031840 MW
- Hockliffe GEC (Ethos Green)HOCKLIFFE GREEN ENERGY CENTRE LTD, Storage with solar or wind, Gate 1Oct 2032850 MW
- Sundon Farm548 UK INVESTMENT HOLDINGS LIMITED, Storage with solar or wind, Gate 1Oct 2032200 MW
- Sundon Farm 2548 UK INVESTMENT HOLDINGS LIMITED, Storage with solar or wind, Gate 1Oct 2032700 MW