Drax 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Drax Solar | East Yorkshire Solar Farm Limited | Solar | 400 | 30 Sep 2029 | Not stated | Scoping |
| Drax BECCS | Drax Power Limited | Thermal (gas, biomass, waste) | 3,906 | 30 Oct 2035 | Not stated | Scoping |
| Drax Power Station | DRAX POWER LIMITED | Thermal (gas, biomass, waste) | 0 | Connected | Not stated | Built |
Left the register since January 2021: Drax (Coal) (0 MW).
Recent changes
- Drax SolarEngland and Wales, SolarCustomer changed from BOOM DEVELOPMENTS LTD to East Yorkshire Solar Farm Limited
- Drax BECCSEngland and Wales, Thermal (gas, biomass, waste)Added to the registerNew
- Drax Power StationEngland and Wales, Thermal (gas, biomass, waste)2,001 MW now connectedConnected
- Drax Power StationEngland and Wales, Thermal (gas, biomass, waste)Capacity changed from 1,905 MW to 3,906 MW
- Drax Power StationEngland and Wales, Thermal (gas, biomass, waste)Renamed from Drax (Biomass)
- Drax (Coal)England and Wales, Thermal (gas, biomass, waste)Left the register (2,001 MW connected)0 MW
- Drax SolarEngland and Wales, SolarCustomer changed from East Yorkshire Solar Farm Limited to BOOM DEVELOPMENTS LTD
- Drax SolarEngland and Wales, SolarCustomer changed from BOOM DEVELOPMENTS LTD to East Yorkshire Solar Farm Limited
- Drax SolarEngland and Wales, SolarConnection date moved from 29 Sep 2029 to 30 Sep 2029 (1 day later)
- Drax SolarEngland and Wales, SolarAdded to the registerNew
- Drax Power StationEngland and Wales, Thermal (gas, biomass, waste)Connection point changed from Drax to Drax 400kV Substation
- Drax (Coal)England and Wales, Thermal (gas, biomass, waste)Connection point changed from Drax to Drax 400kV Substation
- Drax (Coal)England and Wales, Thermal (gas, biomass, waste)Capacity changed from −65 MW to 0 MW
- Drax (Coal)England and Wales, Thermal (gas, biomass, waste)Connection date removed (was 1 Apr 2023)
- Drax (Coal)England and Wales, Thermal (gas, biomass, waste)Connection date moved from 4 Jan 2023 to 1 Apr 2023
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose