Creyke Beck GSP
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Creyke Beck Solar Farm | RWE Renewables UK Solar and Storage Limited | Solar | 320 | 31 May 2033 | Not stated | Scoping |
| KENLEY HOUSE SOLAR PARK | BOOM DEVELOPMENTS LTD | Solar | 150 | 30 Oct 2039 | Not stated | Scoping |
| Pillswood BESS Phase 1 | HEIT PW LIMITED | Storage | 0 | Connected | Not stated | Built |
| Pillswood BESS Phase 2 | HEIT PW2 LIMITED | Storage | 0 | Connected | Not stated | Built |
Recent changes
- Creyke Beck Solar FarmEngland and Wales, SolarCustomer changed from JBM SOLAR PROJECTS 33 LIMITED to RWE Renewables UK Solar and Storage Limited
- KENLEY HOUSE SOLAR PARKEngland and Wales, SolarAdded to the registerNew
- Pillswood BESS Phase 1England and Wales, StorageCustomer changed from Harmony (PW) Limited to HEIT PW LIMITED
- Pillswood BESS Phase 2England and Wales, StorageCustomer changed from Harmony (PW) 2 Limited to HEIT PW2 LIMITED
- Creyke Beck Solar FarmEngland and Wales, SolarAdded to the registerNew
- Pillswood BESS Phase 1England and Wales, Storage49.9 MW now connectedConnected
- Pillswood BESS Phase 1England and Wales, StorageStatus changed from Consents Approved to Built
- Pillswood BESS Phase 2England and Wales, Storage49.9 MW now connectedConnected
- Pillswood BESS Phase 2England and Wales, StorageStatus changed from Consents Approved to Built
- Pillswood BESS Phase 1England and Wales, StorageSubstation name updated in the register (from Creyke Beck to Creyke Beck GSP)
- Pillswood BESS Phase 2England and Wales, StorageSubstation name updated in the register (from Creyke Beck to Creyke Beck GSP)
- Pillswood BESS Phase 1England and Wales, StorageAdded to the registerNew
- Pillswood BESS Phase 2England and Wales, StorageAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?