Chirk GSP
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Blaen y Glyn | BANC DU ENERGY PARK LIMITED | Onshore wind | 46 | 4 Feb 2027 | Not stated | Scoping |
| Bryn Tilti | RHIWLAS ENERGY PARK LIMITED | Onshore wind | 106 | 4 Feb 2027 −17 mo | Not stated | Scoping |
| Dolyfardyn | Llyn Lort Energy Park Limited | Onshore wind | 165 | 4 Feb 2027 | Not stated | Scoping |
| Llwynygog | ESGAIR GALED ENERGY PARK LIMITED | Onshore wind | 125 | 4 Feb 2027 | Not stated | Scoping |
| Moel y Llyn | Waun Hesgog Energy Park Limited | Onshore wind | 251 | 4 Feb 2027 | Not stated | Scoping |
| Maesnant Energy Park | Maesnant Energy Park Limited | Onshore wind | 150 | 1 Nov 2033 | Gate 1 | Scoping |
Recent changes
- Bryn TiltiEngland and Wales, Onshore windConnection date moved from 19 Jul 2028 to 4 Feb 2027 (−17 months)−17 mo
- Maesnant Energy ParkEngland and Wales, Onshore windMarked as Gate 1
- Bryn TiltiEngland and Wales, Onshore windConnection date moved from 4 Feb 2027 to 19 Jul 2028 (+17 months)+17 mo
- Bryn TiltiEngland and Wales, Onshore windAgreement type changed from Direct Connection to Embedded
- Bryn TiltiEngland and Wales, Onshore windAgreement type changed from Embedded to Direct Connection
- Moel y LlynEngland and Wales, Onshore windCustomer changed from Llyn Lort Energy Park Limited to Waun Hesgog Energy Park Limited
- Bryn TiltiEngland and Wales, Onshore windAgreement type changed from Directly Connected to Embedded
- Maesnant Energy ParkEngland and Wales, Onshore windAdded to the registerNew
- Blaen y GlynEngland and Wales, Onshore windSubstation name updated in the register (from Chirk to Chirk GSP)
- Blaen y GlynEngland and Wales, Onshore windAgreement type changed from Directly Connected to Embedded
- Bryn TiltiEngland and Wales, Onshore windSubstation name updated in the register (from Chirk to Chirk GSP)
- Bryn TiltiEngland and Wales, Onshore windAgreement type changed from Embedded to Directly Connected
- DolyfardynEngland and Wales, Onshore windSubstation name updated in the register (from Chirk to Chirk GSP)
- LlwynygogEngland and Wales, Onshore windSubstation name updated in the register (from Chirk to Chirk GSP)
- Moel y LlynEngland and Wales, Onshore windSubstation name updated in the register (from Chirk to Chirk GSP)
- Bryn TiltiEngland and Wales, Onshore windRenamed from Bryn Titli
- DolyfardynEngland and Wales, Onshore windCustomer changed from Lyn Lort Energy Park Limited to Llyn Lort Energy Park Limited
- Moel y LlynEngland and Wales, Onshore windCustomer changed from Lyn Lort Energy Park Limited to Llyn Lort Energy Park Limited
- LlwynygogEngland and Wales, Onshore windAgreement type changed from Directly Connected to Embedded
- Blaen y GlynEngland and Wales, Onshore windAdded to the registerNew
- Bryn TiltiEngland and Wales, Onshore windAdded to the registerNew
- DolyfardynEngland and Wales, Onshore windAdded to the registerNew
- LlwynygogEngland and Wales, Onshore windAdded to the registerNew
- Moel y LlynEngland and Wales, Onshore windAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?