Bryn Tilti
- Connection date
- 4 Feb 2027 −17 months since 9 Dec
- Gate
- Not stated
- Status
- Scoping
- Technology
- Onshore wind
- Total capacity
- 106 MW
- Connected now
- 0 MW
- Still to connect
- 106 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Embedded
- Region
- England and Wales
- Project number
- PRO-001586
- In the register since
- January 2022
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 24 Sep 2026 registerConnection date moved from 19 Jul 2028 to 4 Feb 2027 (−17 months)
- 21 Nov 2025 registerConnection date moved from 4 Feb 2027 to 19 Jul 2028 (+17 months)
- 29 Jul 2025 registerAgreement type changed from Direct Connection to Embedded
- 31 May 2024 registerAgreement type changed from Embedded to Direct Connection
- 30 Jan 2024 registerAgreement type changed from Directly Connected to Embedded
- 23 Dec 2022 registerSubstation name updated in the register (from Chirk to Chirk GSP)
- 23 Dec 2022 registerAgreement type changed from Embedded to Directly Connected
- 30 Mar 2022 registerRenamed from Bryn Titli
- 28 Jan 2022 registerAdded to the register
Also at Chirk GSP
Substation view5 other projects, 843 MW still to connect at this substation in total.
- Blaen y GlynBANC DU ENERGY PARK LIMITED, Onshore wind, Not statedFeb 202746 MW
- DolyfardynLlyn Lort Energy Park Limited, Onshore wind, Not statedFeb 2027165 MW
- LlwynygogESGAIR GALED ENERGY PARK LIMITED, Onshore wind, Not statedFeb 2027125 MW
- Moel y LlynWaun Hesgog Energy Park Limited, Onshore wind, Not statedFeb 2027251 MW
- Maesnant Energy ParkMaesnant Energy Park Limited, Onshore wind, Gate 1Nov 2033150 MW