Bramford B 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Bramford GEC (Ethos Green) | BRAMFORD GREEN ENERGY CENTRE LTD | Storage with solar or wind | 650 | 1 Jun 2032 −17 mo | Gate 1 | Awaiting Consents |
Recent changes
- Bramford GEC (Ethos Green)England and Wales, Storage with solar or windConnection date moved from 30 Oct 2033 to 1 Jun 2032 (−17 months)−17 mo
- Bramford GEC (Ethos Green)England and Wales, Storage with solar or windTechnology changed from Demand, Storage, Solar, Reactive compensation to Storage, Solar
- Bramford GEC (Ethos Green)England and Wales, Storage with solar or windConnection point changed from Bramford 400kV Substation to Bramford B 400kV Substation
- Bramford GEC (Ethos Green)England and Wales, Storage with solar or windMarked as Gate 1
- Bramford GEC (Ethos Green)England and Wales, Storage with solar or windRenamed from Bramford GEC
- Bramford GEC (Ethos Green)England and Wales, Storage with solar or windAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?