Bramford GEC (Ethos Green)
BRAMFORD GREEN ENERGY CENTRE LTD at Bramford B 400kV Substation
- Connection date
- 1 Jun 2032 −17 months since 9 Dec
- Gate
- Gate 1
- Status
- Awaiting Consents
- Technology
- Storage + Solar
- Total capacity
- 650 MW
- Connected now
- 0 MW
- Still to connect
- 650 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-004027
- In the register since
- July 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 10 Oct 2026 registerConnection date moved from 30 Oct 2033 to 1 Jun 2032 (−17 months)
- 7 Aug 2026 registerTechnology changed from Demand, Storage, Solar, Reactive compensation to Storage, Solar
- 26 Jun 2026 registerConnection point changed from Bramford 400kV Substation to Bramford B 400kV Substation
- 26 Jun 2026 registerMarked as Gate 1
- 31 Oct 2023 registerRenamed from Bramford GEC
- 28 Jul 2023 registerAdded to the register
Also at Bramford B 400kV Substation
Substation viewNo other projects in the register at this connection point.