Blackhillock 400kV Substation
North Scotland, SSEN Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Blackhillock Battery | BLACKHILLOCK FLEXPOWER LTD | Storage | 349 | 31 Oct 2028 +12 mo | Gate 2 | Consents Approved |
Left the register since January 2021: ESB Blackhillock Synchronous Compensation (0 MW).
Recent changes
- Blackhillock BatteryNorth Scotland, StorageConnection date moved from 31 Oct 2027 to 31 Oct 2028 (+12 months)+12 mo
- Blackhillock BatteryNorth Scotland, StorageStatus changed from Scoping to Consents Approved
- Blackhillock BatteryNorth Scotland, StorageConnection date moved from 29 Oct 2027 to 31 Oct 2027 (2 days later)
- Blackhillock BatteryNorth Scotland, StorageGiven a Gate 2 connection offerGate 2
- Blackhillock BatteryNorth Scotland, StorageConnection date moved from 31 Oct 2026 to 29 Oct 2027 (+12 months)+12 mo
- Blackhillock BatteryNorth Scotland, StorageConnection point changed from Blackhillock 275kV Substation to Blackhillock 400kV Substation
- Blackhillock BatteryNorth Scotland, StorageSubstation name updated in the register (from Blackhillock 275kV to Blackhillock 275kV Substation)
- Blackhillock BatteryNorth Scotland, StorageCustomer changed from Scot Stability Limited to BLACKHILLOCK FLEXPOWER LTD
- Blackhillock BatteryNorth Scotland, StorageConnection date moved from 31 Aug 2026 to 31 Oct 2026 (+2 months)+2 mo
- Blackhillock BatteryNorth Scotland, StorageAdded to the registerNew
- ESB Blackhillock Synchronous CompensationNorth Scotland, OtherLeft the register (0 MW from 31 Oct 2023)0 MW
- ESB Blackhillock Synchronous CompensationNorth Scotland, OtherAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?