Blackhillock Battery
- Connection date
- 31 Oct 2028 +12 months since 9 Dec
- Gate
- Gate 2
- Status
- Consents Approved
- Technology
- Storage
- Total capacity
- 349 MW
- Connected now
- 0 MW
- Still to connect
- 349 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-001970
- In the register since
- June 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 12 Jun 2026 registerConnection date moved from 31 Oct 2027 to 31 Oct 2028 (+12 months)
- 12 Jun 2026 registerStatus changed from Scoping to Consents Approved
- 5 Jun 2026 registerConnection date moved from 29 Oct 2027 to 31 Oct 2027 (2 days later)
- 5 Jun 2026 registerGiven a Gate 2 connection offer
- 21 Nov 2025 registerConnection date moved from 31 Oct 2026 to 29 Oct 2027 (+12 months)
- 26 Mar 2024 registerConnection point changed from Blackhillock 275kV Substation to Blackhillock 400kV Substation
- 23 Dec 2022 registerSubstation name updated in the register (from Blackhillock 275kV to Blackhillock 275kV Substation)
- 29 Jul 2022 registerCustomer changed from Scot Stability Limited to BLACKHILLOCK FLEXPOWER LTD
- 29 Jul 2022 registerConnection date moved from 31 Aug 2026 to 31 Oct 2026 (+2 months)
- 30 Jun 2022 registerAdded to the register
Also at Blackhillock 400kV Substation
Substation viewNo other projects in the register at this connection point.