Blackhillock 275kV Substation
North Scotland, SSEN Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Zenobe Blackhillock 300 MW | ZENOBE BLACKHILLOCK LIMITED | Storage | 100 | 1 Apr 2026 Past date | Not stated | Consents Approved |
| Kedrum Solar Farm | Rosside Energy Limited | Storage with solar or wind | 150 | 30 May 2030 | Not stated | Awaiting Consents |
Recent changes
- Kedrum Solar FarmNorth Scotland, Storage with solar or windStatus changed from Scoping to Awaiting Consents
- Kedrum Solar FarmNorth Scotland, Storage with solar or windTechnology changed from Storage to Storage, Solar
- Zenobe Blackhillock 300 MWNorth Scotland, StorageStage 2: Status changed from Built to Consents Approved
- Zenobe Blackhillock 300 MWNorth Scotland, StorageStage 1: 10 MW no longer connected
- Zenobe Blackhillock 300 MWNorth Scotland, StorageStage 1: Connection date removed (was 22 Nov 2024)
- Zenobe Blackhillock 300 MWNorth Scotland, StorageStage 2: 210 MW no longer connected
- Zenobe Blackhillock 300 MWNorth Scotland, StorageStage 2: Capacity changed from 90 MW to 100 MW
- Zenobe Blackhillock 300 MWNorth Scotland, StorageStage removed (210 MW connected)
- Zenobe Blackhillock 300 MWNorth Scotland, StorageStage 1: 10 MW now connectedConnected
- Zenobe Blackhillock 300 MWNorth Scotland, StorageStage 1: Capacity changed from 200 MW to 210 MW
- Zenobe Blackhillock 300 MWNorth Scotland, StorageStage 1: Connection date set to 22 Nov 2024
- Zenobe Blackhillock 300 MWNorth Scotland, StorageStage 2: 210 MW now connectedConnected
- Zenobe Blackhillock 300 MWNorth Scotland, StorageStage 2: Capacity changed from 100 MW to 300 MW
- Zenobe Blackhillock 300 MWNorth Scotland, StorageStage 2: Status changed from Consents Approved to Built
- Zenobe Blackhillock 300 MWNorth Scotland, StorageNew stage added (210 MW connected)
- Zenobe Blackhillock 300 MWNorth Scotland, StorageStage 1: 200 MW now connectedConnected
- Zenobe Blackhillock 300 MWNorth Scotland, StorageStage 1: Status changed from Consents Approved to Built
- Zenobe Blackhillock 300 MWNorth Scotland, StorageStage 1: Connection date moved from 1 Feb 2024 to 22 Nov 2024 (+10 months)+10 mo
- Kedrum Solar FarmNorth Scotland, Storage with solar or windTechnology changed from Solar to Storage
- Zenobe Blackhillock 300 MWNorth Scotland, StorageRenamed from Zenobe Blackhillock 200 MW
- Kedrum Solar FarmNorth Scotland, Storage with solar or windAdded to the registerNew
- Zenobe Blackhillock 300 MWNorth Scotland, StorageSubstation name updated in the register (from Blackhillock 275kV to Blackhillock 275kV Substation)
- Zenobe Blackhillock 300 MWNorth Scotland, StorageRestructured from 1 stage (200 MW from 31 Oct 2023) to 2 stages (200 MW from 1 Feb 2024, 100 MW from 1 Apr 2026). First connection date +3 months+3 mo
- Zenobe Blackhillock 300 MWNorth Scotland, StorageStage removed (0 MW)
- Zenobe Blackhillock 300 MWNorth Scotland, StorageNew stage added (0 MW)
- Zenobe Blackhillock 300 MWNorth Scotland, StorageAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose