Zenobe Blackhillock 300 MW
ZENOBE BLACKHILLOCK LIMITED at Blackhillock 275kV Substation
- Connection date
- 1 Apr 2026
- Gate
- Not stated
- Status
- Consents Approved
- Technology
- Storage
- Total capacity
- 300 MW
- Connected now
- 200 MW
- Still to connect
- 100 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-001624
- In the register since
- August 2021
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 200 | 0 | 200 | None | Not stated | Built |
| 2 | 0 | 100 | 300 | 1 Apr 2026 | Not stated | Consents Approved |
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 31 Oct 2025 registerStage 2: Status changed from Built to Consents Approved
- 30 Sep 2025 registerStage 1: 10 MW no longer connected
- 30 Sep 2025 registerStage 1: Connection date removed (was 22 Nov 2024)
- 30 Sep 2025 registerStage 2: 210 MW no longer connected
- 30 Sep 2025 registerStage 2: Capacity changed from 90 MW to 100 MW
- 30 Sep 2025 registerStage removed (210 MW connected)
- 29 Jul 2025 registerStage 1: 10 MW now connected
- 29 Jul 2025 registerStage 1: Capacity changed from 200 MW to 210 MW
- 29 Jul 2025 registerStage 1: Connection date set to 22 Nov 2024
- 29 Jul 2025 registerStage 2: 210 MW now connected
- 29 Jul 2025 registerStage 2: Capacity changed from 100 MW to 300 MW
- 29 Jul 2025 registerStage 2: Status changed from Consents Approved to Built
- 29 Jul 2025 registerNew stage added (210 MW connected)
- 29 Apr 2025 registerStage 1: 200 MW now connected
- 29 Apr 2025 registerStage 1: Status changed from Consents Approved to Built
- 28 Feb 2025 registerStage 1: Connection date moved from 1 Feb 2024 to 22 Nov 2024 (+10 months)
- 29 Dec 2023 registerRenamed from Zenobe Blackhillock 200 MW
- 23 Dec 2022 registerSubstation name updated in the register (from Blackhillock 275kV to Blackhillock 275kV Substation)
- 29 Nov 2022 registerRestructured from 1 stage (200 MW from 31 Oct 2023) to 2 stages (200 MW from 1 Feb 2024, 100 MW from 1 Apr 2026). First connection date +3 months
- 29 Oct 2021 registerStage removed (0 MW)
- 28 Sep 2021 registerNew stage added (0 MW)
- 31 Aug 2021 registerAdded to the register
Also at Blackhillock 275kV Substation
Substation view1 other project, 250 MW still to connect at this substation in total.